1834 N WESTERLY TER 90026
Certificate Information: 1834 N WESTERLY TER 90026
- Application / Permit
- 20030-30000-02947
- Plan Check / Job No.
- B20WL02438
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- grading for addition/remodel to s.f.d., new detached garage, new site retaining wall and new pool.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/26/2025
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/6/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/7/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| Plan Check Approved | 3/9/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/22/2021 | APPLICANT |
| Permit Finaled | 2/26/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 11/17/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Caire John Construction Inc; Lic. No.: 626684-B | 2028 LOMBARDY DR LA CANADA, CA 91011 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Sin,, Felix Kin Hung; Lic. No.: C68203 | 105 PISMO DR CARSON, CA 90745 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/5/2021 | Corrections Issued | ROBERT HUGHES |
| Initial Grading | 11/24/2021 | Approved | ROBERT HUGHES |
| Excavation | 2/16/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 2/22/2022 | Approved | ALEXANDER HELFER |
| Excavation | 9/8/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 10/14/2022 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 3/28/2024 | Corrections Issued | ALEXANDER HELFER |
| Sub-Drain | 4/2/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/5/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Approved Compaction Report | 6/28/2024 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 8/9/2024 | Partial Approval | ALEXANDER HELFER |
| Excavation | 8/9/2024 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 2/4/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 2/18/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 2/18/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Rough | 2/18/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 2/26/2025 | Permit Finaled | RUSSELL BONVOULOIR |