2175 N MANDEVILLE CANYON ROAD 90049

Certificate Information: 2175 N MANDEVILLE CANYON ROAD 90049

Application / Permit
20030-20000-05916
Plan Check / Job No.
B20VN13650
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EXCAVATION FOR (N) POOL/SPA -- HILLSIDE GRADING AREA
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
Permit Finaled on 4/1/2025

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 NILOOFAR MEHRAIN
Corrections Issued 11/17/2020 NILOOFAR MEHRAIN
Quality Review Completed 11/17/2020 CHON CHIO KUO
Applicant returned to address corrections 12/15/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/15/2021 NILOOFAR MEHRAIN
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
Permit Finaled 3/28/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/15/2021 NILOOFAR MEHRAIN
Miscellaneous Cleared 1/21/2021 MARC WOERSCHING
Miscellaneous Cleared 1/21/2021 MARC WOERSCHING
Private street Cleared 1/21/2021 MARC WOERSCHING
ZA Case Cleared 1/21/2021 MARC WOERSCHING
Eng Process Fee Ord 176,300 Cleared 1/26/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 1/26/2021 ANTHONY MAINEZ

Contact Information

Contractor Ahern Construction Corporation; Lic. No.: 687780-B 3835-R THOUSAND OAKS BLVD   #118    WESTLAKE VILLAGE, CA 91362
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 3/9/2021 Partial Approval MATTHEW JENKINS
Excavation 6/18/2021 Partial Inspection MATTHEW JENKINS
FLOOD-Proofing Certificate 8/31/2021 Not Ready for Inspection VASIL MIHALEV
Rough 8/31/2021 Partial Inspection MATTHEW JENKINS
Special/Order Compliance 4/26/2022 Partial Inspection KIRK LINKLATER
Bottom/Toe 2/27/2023 Partial Inspection MATTHEW JENKINS
Final 2/27/2023 Partial Inspection MATTHEW JENKINS
Rough 2/27/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 3/28/2025 Approved JOHNNY MIRANDA
Final 3/28/2025 Permit Finaled JOHNNY MIRANDA
Rough 3/28/2025 Approved JOHNNY MIRANDA