3535 N HILLVIEW PL 90032
Certificate Information: 3535 N HILLVIEW PL 90032
- Application / Permit
- 20030-20000-03647
- Plan Check / Job No.
- B20VN04785
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- NEW GRADING FOR NEW SFD W ATTACHED GARAGE AND RETAINING WALL
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/9/2025
Permit Application Status History
| Submitted | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | RARES BODEA |
| Green Plans Picked Up | 4/17/2020 | APPLICANT |
| Corrections Issued | 4/23/2020 | RARES BODEA |
| Quality Review Completed | 4/30/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 7/15/2020 | RARES BODEA |
| Applicant returned to address corrections | 10/24/2022 | RARES BODEA |
| Applicant returned to address corrections | 12/13/2022 | RARES BODEA |
| Applicant returned to address corrections | 1/23/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/1/2023 | RARES BODEA |
| Plan Check Approved | 2/3/2023 | RARES BODEA |
| Issued | 4/26/2023 | APPLICANT |
| Permit Finaled | 7/9/2025 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/9/2021 | JASON CHAN |
| "Q" conditions | Cleared | 4/9/2021 | JASON CHAN |
| ZI | Cleared | 4/9/2021 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 1/23/2023 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/9/2023 | Corrections Issued | ROBERT HUGHES |
| Excavation | 10/31/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 12/19/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 12/27/2023 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/2/2024 | Partial Approval | LANNY MERRICK |
| Initial Grading | 5/2/2024 | Partial Inspection | LANNY MERRICK |
| Sub-Drain | 5/28/2024 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 6/12/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/18/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Final | 4/18/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Rough | 4/18/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 4/25/2025 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 5/7/2025 | Approved | RAMAZANALI ALMASI |
| Final | 5/7/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Rough | 5/7/2025 | Approved | RAMAZANALI ALMASI |
| Final | 6/5/2025 | Partial Approval | RAMAZANALI ALMASI |
| Final | 7/9/2025 | Permit Finaled | RAMAZANALI ALMASI |