2112 N ROSCOMARE ROAD 90077

Certificate Information: 2112 N ROSCOMARE ROAD 90077

Application / Permit
20030-20000-03382
Plan Check / Job No.
B20VN08707
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING RECOMPACTION AND BACKFILL FOR RETAINING WALLS AND SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/27/2021
Issuing Office
Valley
Current Status
Permit Finaled on 5/7/2025

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SERGIO MUNIZ
Corrections Issued 7/31/2020 SERGIO MUNIZ
Quality Review Completed 8/31/2020 OMID HEDAYAT
Applicant returned to address corrections 5/11/2021 SERGIO MUNIZ
Applicant returned to address corrections 6/8/2021 SERGIO MUNIZ
Plan Check Approved 8/6/2021 SERGIO MUNIZ
Issued 8/27/2021 APPLICANT
Building Plans Picked Up 8/27/2021 APPLICANT
Permit Finaled 5/6/2025 MATTHEW JENKINS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/6/2021 BRIAN OLSON

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201
Landscape Architect Alaniz,, Arthur Louis; Lic. No.: LA5554 26 CLEAR VISTA      ROLLING HILLS ESTATES, CA 90274

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 9/9/2021 Partial Inspection BRIAN OLSON
Initial Grading 12/15/2021 Approved CHARLES POWELL
Initial Grading 1/6/2022 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 1/21/2022 Partial Approval CHARLES POWELL
Excavation 1/21/2022 Partial Approval CHARLES POWELL
Sub-Drain 7/13/2022 Partial Approval CHARLES POWELL
Fill/Backfill 7/26/2022 Partial Approval CHARLES POWELL
Sub-Drain 7/26/2022 Not Ready for Inspection CHARLES POWELL
Sub-Drain 4/6/2023 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 4/20/2023 Not Ready for Inspection VASIL MIHALEV
Sub-Drain 4/20/2023 Not Ready for Inspection VASIL MIHALEV
Bottom/Toe 2/26/2025 Approved VASIL MIHALEV
Final 2/26/2025 Corrections Issued VASIL MIHALEV
Rough 2/26/2025 Approved VASIL MIHALEV
Approved Compaction Report 3/7/2025 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 4/10/2025 Corrections Issued MATTHEW JENKINS
Final 4/14/2025 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 4/21/2025 Approved MATTHEW JENKINS
Final 4/22/2025 Corrections Issued MATTHEW JENKINS
Final 5/6/2025 Permit Finaled MATTHEW JENKINS