1451 S GLENVILLE DR 90035
Certificate Information: 1451 S GLENVILLE DR 90035
- Application / Permit
- 20030-20000-01666
- Plan Check / Job No.
- B20VN04726
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- (2 OF 2) GRADING FOR BASEMENT OF SFD
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/24/2021
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 5/6/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/18/2020 | KESETE HAREGOT |
| Green Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 7/14/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/16/2020 | SERGIO GUTIERREZ |
| Issued | 7/17/2020 | APPLICANT |
| Building Plans Picked Up | 7/21/2020 | APPLICANT |
| Permit Finaled | 5/21/2021 | KIRK LINKLATER |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 7/14/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/14/2020 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 7/14/2020 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/28/2020 | Corrections Issued | MATTHEW JENKINS |
| Initial Grading | 7/30/2020 | Approved | BRIAN OLSON |
| Sub-Drain | 8/25/2020 | Partial Approval | BRIAN OLSON |
| Sub-Drain | 10/19/2020 | Not Ready for Inspection | BRIAN OLSON |
| Sub-Drain | 10/20/2020 | Partial Approval | KIRK LINKLATER |
| Excavation | 2/25/2021 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 5/4/2021 | Approved | KIRK LINKLATER |
| Bottom/Toe | 5/11/2021 | Not Ready for Inspection | JONATHAN HOM |
| Final | 5/11/2021 | Corrections Issued | JONATHAN HOM |
| Rough | 5/11/2021 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 5/21/2021 | Approved | KIRK LINKLATER |
| Final | 5/21/2021 | Permit Finaled | KIRK LINKLATER |
| Rough | 5/21/2021 | Approved | KIRK LINKLATER |