900 N VISTA ST 90046
Certificate Information: 900 N VISTA ST 90046
- Application / Permit
- 20030-20000-01075
- Plan Check / Job No.
- B20VN03044
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading Permit for the proposed Retaining Wall Excavation & Backfill.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/28/2024
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | ALDOUS CHIC |
| Corrections Issued | 3/16/2020 | ALDOUS CHIC |
| Quality Review Completed | 3/17/2020 | ABDUL CHEGENI |
| Building Plans Picked Up | 3/19/2020 | APPLICANT |
| Applicant returned to address corrections | 3/8/2021 | OMID HEDAYAT |
| Plan Check Approved | 3/8/2021 | OMID HEDAYAT |
| Issued | 3/25/2021 | APPLICANT |
| Permit Finaled | 3/27/2024 | JONATHAN HOM |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | M K Builders; Lic. No.: 907501-B | 1103 WEST 160TH STREET GARDENA, CA 90247 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 4/12/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation | 4/13/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 4/15/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 4/19/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 6/2/2021 | Approved | VASIL MIHALEV |
| Special/Order Compliance | 8/10/2021 | Partial Inspection | ALEXANDER HELFER |
| Bottom/Toe | 1/26/2024 | Corrections Issued | ALEXANDER HELFER |
| Final | 1/26/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 1/26/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Approved Compaction Report | 2/20/2024 | Approved | MICHAEL TEMPLE |
| Bottom/Toe | 3/20/2024 | Not Ready for Inspection | JONATHAN HOM |
| Final | 3/20/2024 | Not Ready for Inspection | JONATHAN HOM |
| Rough | 3/20/2024 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 3/22/2024 | Partial Inspection | JONATHAN HOM |
| Final | 3/22/2024 | Partial Inspection | JONATHAN HOM |
| Rough | 3/22/2024 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 3/27/2024 | Approved | JONATHAN HOM |
| Final | 3/27/2024 | Permit Finaled | JONATHAN HOM |
| Rough | 3/27/2024 | Approved | JONATHAN HOM |