1065 N CHANTILLY ROAD 90077
Certificate Information: 1065 N CHANTILLY ROAD 90077
- Application / Permit
- 20030-20000-00557
- Plan Check / Job No.
- B20VN01484
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR POOL AND RETAINING WALLS. (482 CY).
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 9/27/2022
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/10/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Applicant returned to address corrections | 10/19/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 1/6/2021 | TROY DEGUZMAN |
| Plan Check Approved | 2/23/2021 | TROY DEGUZMAN |
| Issued | 3/18/2021 | APPLICANT |
| Permit Finaled | 9/27/2022 | CHARLES POWELL |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/5/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 1/5/2021 | TROY DEGUZMAN |
| Excavation more than 5-ft deep | Cleared | 2/2/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Bel Air Builders Inc; Lic. No.: 872640-B | 17220 SUNBURST STREET NORTHRIDGE, CA 91325 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 5/6/2021 | Corrections Issued | BRIAN OLSON |
| Initial Grading | 5/6/2021 | Not Ready for Inspection | BRIAN OLSON |
| Initial Grading | 5/17/2021 | Approved | BRIAN OLSON |
| Sub-Drain | 6/7/2021 | Partial Approval | BRIAN OLSON |
| Sub-Drain | 6/21/2021 | Partial Inspection | BRIAN OLSON |
| Sub-Drain | 6/23/2021 | Partial Approval | BRIAN OLSON |
| Bottom/Toe | 8/9/2021 | Approved | JONATHAN HOM |
| Excavation | 8/9/2021 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 12/6/2021 | Partial Approval | CHARLES POWELL |
| Final | 4/4/2022 | Not Ready for Inspection | CHARLES POWELL |
| Rough | 4/4/2022 | Approved | CHARLES POWELL |
| Final | 5/19/2022 | Partial Approval | CHARLES POWELL |
| Final | 9/22/2022 | Partial Approval | CHARLES POWELL |
| Final | 9/27/2022 | Permit Finaled | CHARLES POWELL |