6100 N WOODLEY AVE 91436
Certificate Information: 6100 N WOODLEY AVE 91436
- Application / Permit
- 20030-20000-00551
- Plan Check / Job No.
- B20VN01473
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR SITE, CUT 4195 CY, FILL 929 CY EXPORT 3266CY , & REMOVE & RECOMPACT MAX. 5' DEEP 10983 CY
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/2/2025
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | CHON CHIO KUO |
| Corrections Issued | 4/13/2020 | CHON CHIO KUO |
| Quality Review Completed | 4/15/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 4/17/2020 | APPLICANT |
| Green Plans Picked Up | 4/17/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/10/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/24/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/30/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/1/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/7/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/8/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/13/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/17/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/21/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/20/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/27/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/1/2021 | CHON CHIO KUO |
| Plan Check Approved | 2/4/2021 | CHON CHIO KUO |
| Issued | 9/2/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/18/2020 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 8/18/2020 | LOUIS ORTEGA |
| ZA Case | Cleared | 8/18/2020 | LOUIS ORTEGA |
| ZA Case | Cleared | 8/18/2020 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Permit | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 8/20/2020 | LEE GUILBEAUX |
| Metro Rail approval | Cleared | 8/24/2020 | CHON CHIO KUO |
| Low Impact Development | Cleared | 9/1/2020 | AMMAR ELTAWIL |
| Excavation more than 5-ft deep | Cleared | 9/9/2020 | CALOSHA APPROVED |
| ZI | Cleared | 9/30/2020 | LOUIS ORTEGA |
Contact Information
| Contractor | Ford E C Inc; Lic. No.: 396212-B | 10850 WILSHIRE BLVD 1120 LOS ANGELES, CA 90024 |
| Engineer | Aoanan,, Virgilio Cendana; Lic. No.: C36079 | 1041 S GARFIELD AVE STE #210 ALHAMBRA, CA 91801 |
| Engineer | Islam,, Mohammed Saiful; Lic. No.: S4083 | 155 N LAKE AVE SUITE 600 PASADENA, CA 91101 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/29/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 10/1/2025 | Approved | MANUEL TEJADA |
| Bottom/Toe | 12/10/2025 | Partial Approval | MANUEL TEJADA |
| Deputy Grading | 12/10/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/11/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 12/12/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 12/15/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/16/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/18/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/19/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/22/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/23/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 1/23/2026 | Approved | MANUEL TEJADA |
| Deputy Grading | 1/26/2026 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 1/27/2026 | Approved | ROBERT PINA |
| Deputy Grading | 1/28/2026 | Approved | ROBERT PINA |
| Deputy Grading | 1/29/2026 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 2/9/2026 | Approved | MANUEL TEJADA |
| Deputy Grading | 2/10/2026 | Partial Approval | MANUEL TEJADA |
| Approved Compaction Report | 2/11/2026 | Approved | MANUEL TEJADA |
| Deputy Grading | 2/11/2026 | No Access for Inspection | MANUEL TEJADA |
| Deputy Grading | 2/12/2026 | Approved | MANUEL TEJADA |
| Deputy Grading | 2/13/2026 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 3/23/2026 | Approved | MANUEL TEJADA |
| Sub-Drain | 7/8/2026 | Approved | MANUEL TEJADA |