Approved Compaction Report
|
6/22/2022
|
Not Ready for Inspection
|
JONATHAN HOM
|
|
Bottom/Toe
|
6/22/2022
|
Not Ready for Inspection
|
JONATHAN HOM
|
|
Rough
|
6/22/2022
|
Not Ready for Inspection
|
JONATHAN HOM
|
|
SWPPP-Const. Storm Water
|
6/22/2022
|
Not Required
|
JONATHAN HOM
|
|
Initial Grading
|
6/24/2022
|
Approved
|
JONATHAN HOM
|
|
Deputy Grading
|
6/27/2022
|
Approved
|
JONATHAN HOM
|
|
Excavation
|
6/27/2022
|
Partial Approval
|
JONATHAN HOM
|
|
Bottom/Toe
|
6/28/2022
|
Partial Approval
|
JONATHAN HOM
|
|
Deputy Grading
|
6/28/2022
|
Approved
|
JONATHAN HOM
|
|
Excavation
|
6/28/2022
|
Partial Inspection
|
JONATHAN HOM
|
|
SWPPP-Const. Storm Water
|
6/28/2022
|
Not Required
|
JONATHAN HOM
|
|
Deputy Grading
|
6/29/2022
|
Conditional Approval
|
AL GAMBLE
|
|
Excavation
|
6/29/2022
|
Partial Inspection
|
AL GAMBLE
|
|
Deputy Grading
|
6/30/2022
|
Approved
|
KIRK LINKLATER
|
|
Approved Compaction Report
|
7/1/2022
|
Not Ready for Inspection
|
JONATHAN HOM
|
|
Bottom/Toe
|
7/1/2022
|
Partial Approval
|
JONATHAN HOM
|
|
Initial Grading
|
7/1/2022
|
Partial Inspection
|
JONATHAN HOM
|
|
Rough
|
7/1/2022
|
Partial Inspection
|
JONATHAN HOM
|
|
Deputy Grading
|
7/5/2022
|
Approved
|
JONATHAN HOM
|
|
Deputy Grading
|
7/6/2022
|
Approved
|
JONATHAN HOM
|
|
Deputy Grading
|
7/7/2022
|
Approved
|
JONATHAN HOM
|
|
Deputy Grading
|
7/8/2022
|
Approved
|
JONATHAN HOM
|
|
Approved Compaction Report
|
8/22/2022
|
Approved
|
JONATHAN HOM
|
|
Excavation
|
12/27/2022
|
Partial Inspection
|
JONATHAN HOM
|
|
Drainage Devices/Catch Basin
|
1/31/2023
|
Partial Approval
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/2/2023
|
Not Ready for Inspection
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/6/2023
|
Partial Approval
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/7/2023
|
Partial Approval
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/8/2023
|
Partial Approval
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/9/2023
|
Approved
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/10/2023
|
Approved
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/13/2023
|
Not Ready for Inspection
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/14/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
2/15/2023
|
Partial Approval
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
2/16/2023
|
Partial Inspection
|
AL GAMBLE
|
|
Private Sewage Disposal System
|
4/5/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/7/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/11/2023
|
Approved
|
VASIL MIHALEV
|
|
Drainage Devices/Catch Basin
|
4/12/2023
|
Partial Approval
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/14/2023
|
Partial Approval
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/17/2023
|
Partial Approval
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/18/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/19/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Fill/Backfill
|
4/19/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Initial Grading
|
4/19/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
4/28/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/2/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/4/2023
|
Partial Approval
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/17/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Fill/Backfill
|
5/17/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/18/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Fill/Backfill
|
5/18/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/19/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Fill/Backfill
|
5/19/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/23/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/24/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Drainage Devices/Catch Basin
|
5/25/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Rough
|
5/31/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
SWPPP-Const. Storm Water
|
6/1/2023
|
Not Required
|
MATTHEW JENKINS
|
|
Irrigation/Landscape
|
6/2/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Rough
|
6/2/2023
|
Partial Inspection
|
MATTHEW JENKINS
|
|
Irrigation/Landscape
|
8/29/2023
|
Partial Inspection
|
AL GAMBLE
|
|
Sub-Drain
|
11/21/2023
|
Approved
|
AL GAMBLE
|
|
Bottom/Toe
|
12/15/2023
|
Partial Inspection
|
AL GAMBLE
|
|
Drainage Devices/Catch Basin
|
12/15/2023
|
Partial Approval
|
AL GAMBLE
|
|
Final
|
12/15/2023
|
Partial Inspection
|
AL GAMBLE
|
|
Rough
|
12/15/2023
|
Partial Inspection
|
AL GAMBLE
|
|
Approved Compaction Report
|
1/10/2024
|
Approved
|
VASIL MIHALEV
|
|
Bottom/Toe
|
1/29/2024
|
Approved
|
AL GAMBLE
|
|
Final
|
1/29/2024
|
Permit Finaled
|
AL GAMBLE
|
|
Rough
|
1/29/2024
|
Approved
|
AL GAMBLE
|
|
SWPPP-Const. Storm Water
|
1/29/2024
|
Completed
|
AL GAMBLE
|