15500 N STEPHEN S WISE DR 90077
Certificate Information: 15500 N STEPHEN S WISE DR 90077
- Application / Permit
- 20030-10000-07335
- Plan Check / Job No.
- B20LA23504
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE PREP FOR PROPOSED BUILDING
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/2/2025
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 2/9/2021 | APPLICANT |
| Corrections Issued | 2/22/2021 | HERNAN ARREOLA |
| Quality Review Completed | 2/23/2021 | JASON HEALEY |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/4/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/5/2021 | HERNAN ARREOLA |
| Green Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/19/2022 | HERNAN ARREOLA |
| Plan Check Approved | 10/28/2022 | HERNAN ARREOLA |
| Issued | 11/14/2022 | APPLICANT |
| Permit Finaled | 4/1/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Abramson,, Trevor David; Lic. No.: C17597 | 5171 W JEFFERSON BLVD. LOS ANGELES, CA 90016 |
| Contractor | Del Amo Construction Inc; Lic. No.: 744458-B | 23840 MADISON STREET TORRANCE, CA 90505 |
| Engineer | Adams,, Jelisa; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
| Engineer | John,, Benjamin Morgan; Lic. No.: C86018 | 1541 SE MAPLE AVE PORTLAND, OR 97214 |
| Engineer | Zen,, Petrina; Lic. No.: C87489 | 905 PIEDMONT IRVINE, CA 92620 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 11/16/2022 | Partial Approval | CHARLES POWELL |
| Initial Grading | 11/17/2022 | Approved | CHARLES POWELL |
| Bottom/Toe | 2/7/2023 | Partial Approval | CHARLES POWELL |
| Excavation | 3/13/2023 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 4/26/2023 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 5/1/2023 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 5/2/2023 | Approved | CHARLES POWELL |
| Bottom/Toe | 5/3/2023 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 5/3/2023 | Approved | CHARLES POWELL |
| Bottom/Toe | 5/9/2023 | Approved | VASIL MIHALEV |
| Fill/Backfill | 5/16/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 6/2/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Initial Grading | 7/5/2023 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Grading | 7/7/2023 | Corrections Issued | CHARLES POWELL |
| Approved Compaction Report | 7/31/2023 | Corrections Issued | CHARLES POWELL |
| Sub-Drain | 8/1/2023 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 8/15/2023 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 8/17/2023 | Approved | VASIL MIHALEV |
| Sub-Drain | 10/13/2023 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 12/22/2023 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 2/14/2024 | Approved | ROBERT PINA |
| Drainage Devices/Catch Basin | 2/15/2024 | Partial Approval | ROBERT PINA |
| Sub-Drain | 2/28/2024 | Partial Approval | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 4/23/2024 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sub-Drain | 5/15/2024 | Approved | VASIL MIHALEV |
| Drainage Devices/Catch Basin | 5/21/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 5/21/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 9/19/2024 | Partial Approval | JOHNNY MIRANDA |
| Final | 2/12/2025 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 2/12/2025 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 2/18/2025 | Approved | JOHNNY MIRANDA |
| Final | 4/1/2025 | Permit Finaled | JOHNNY MIRANDA |