127 E NAPOLEON ST 90293
Certificate Information: 127 E NAPOLEON ST 90293
- Application / Permit
- 20030-10000-07298
- Plan Check / Job No.
- G20LA00277
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- SLOPE REPAIR TO RESTORE LATERAL SUPPORT. CUT: +/- 43 C.Y. FILL: +/- 13 C.Y. 2 OF 2
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/1/2021
Permit Application Status History
| Submitted | 12/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2021 | DAN RYAN EVANGELISTA |
| Corrections Issued | 1/11/2021 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 6/16/2021 | DAN RYAN EVANGELISTA |
| Issued | 6/24/2021 | APPLICANT |
| Permit Finaled | 11/30/2021 | JONATHAN HOM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | DINAH GARIN |
| Coastal Zone | Cleared | 4/29/2021 | RICHARD REASER |
| Grading Pre-Inspection | Cleared | 5/5/2021 | KIRK LINKLATER |
| Excavation more than 5-ft deep | Cleared | 6/16/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Coast Construction And Foundation Repair Inc; Lic. No.: 1007583-A | 302 FRASER LANE VENTURA, CA 93001 |
| Engineer | Samara,, Muzahim Ali; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Carnegie,, Vincent John; Lic. No.: EG1608 | P.O. BOX 5444 GLENDALE, CA 912012036 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/13/2021 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 7/19/2021 | Approved | JONATHAN HOM |
| Bottom/Toe | 7/22/2021 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 7/27/2021 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 8/30/2021 | Approved | JONATHAN HOM |
| Drainage Devices/Catch Basin | 9/13/2021 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 11/4/2021 | Approved | JONATHAN HOM |
| Bottom/Toe | 11/15/2021 | Approved | JONATHAN HOM |
| Final | 11/15/2021 | Partial Inspection | JONATHAN HOM |
| Rough | 11/15/2021 | Approved | JONATHAN HOM |
| Final | 11/30/2021 | Permit Finaled | JONATHAN HOM |