923-935 S KENMORE AVE 90006
Certificate Information: 923-935 S KENMORE AVE 90006
- Application / Permit
- 20030-10000-06792
- Plan Check / Job No.
- B20LA21814
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR NEW RESIDENTIAL APARTMENT COMPLEX.
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2023
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | JOE VO |
| Corrections Issued | 12/10/2020 | JOE VO |
| Quality Review Completed | 12/18/2020 | MINYE PAK |
| Building Plans Picked Up | 12/29/2020 | APPLICANT |
| Plan Check Approved | 4/5/2021 | JOE VO |
| Issued | 4/16/2021 | APPLICANT |
| Permit Finaled | 8/17/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 12/14/2020 | CHIU TAM |
| Low Impact Development | Cleared | 12/15/2020 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 12/29/2020 | TERRY PHAN |
| Historic Resource Verification | Cleared | 3/1/2021 | MICAELA TORRES-GIL |
| Excavation more than 5-ft deep | Cleared | 3/4/2021 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 3/4/2021 | JOE VO |
| Redevelopment Project Area | Cleared | 3/4/2021 | GISELLE CORELLA |
Contact Information
| Contractor | Alpha Construction Co Inc; Lic. No.: 241368-B | 14601 AETNA STREET VAN NUYS, CA 91411 |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/5/2021 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 5/12/2021 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 5/14/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 5/14/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 5/17/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 5/18/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 5/18/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 5/19/2021 | Conditional Approval | ALEXANDER HELFER |
| Excavation | 5/19/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Fill/Backfill | 5/19/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Deputy Grading | 5/25/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 5/26/2021 | Approved | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 5/26/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 6/1/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 6/2/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/2/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/3/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/4/2021 | Approved | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 6/7/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/8/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/9/2021 | Approved | PATRICK MISCHLICH |
| Deputy Grading | 6/10/2021 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 6/10/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 6/10/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/11/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 6/11/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 6/14/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/15/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 6/16/2021 | Approved | ROBERT HUGHES |
| Approved Compaction Report | 7/9/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Approved Compaction Report | 7/12/2021 | Approved | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 8/18/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 12/7/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 2/15/2023 | Conditional Approval | JONATHAN HOM |
| Approved Compaction Report | 7/21/2023 | Approved | ROBERT HUGHES |
| Final | 8/17/2023 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 8/17/2023 | Approved | RUSSELL BONVOULOIR |