9502 N VAN NUYS BLVD 91402

Certificate Information: 9502 N VAN NUYS BLVD 91402

Application / Permit
20030-10000-06534
Plan Check / Job No.
B20LA21197
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
REMOVE AND RECOMPACTION AND SITE GRADING FOR NEW RESIDENTIAL APARTMENT BUILDING.
Permit Issued
Issued on 5/4/2021
Issuing Office
Current Status
Permit Finaled on 4/3/2023

Permit Application Status History

Submitted 1/18/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 FARSHAD ALIMOHAMADI
Corrections Issued 2/2/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 2/2/2021 STANLEY RAAP
Building Plans Picked Up 2/11/2021 APPLICANT
Plan Check Approved 4/30/2021 FARSHAD ALIMOHAMADI
Issued 5/4/2021 APPLICANT
Permit Finaled 3/31/2023 ROBERT PINA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Alpha Construction Co Inc; Lic. No.: 241368-B 14601 AETNA STREET      VAN NUYS, CA 91411

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 6/2/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/14/2021 Approved ALEXANDER ANDREWS
Bottom/Toe 6/15/2021 Partial Approval ALEXANDER ANDREWS
Deputy Grading 6/15/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/16/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/17/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/18/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/21/2021 Approved ALEXANDER ANDREWS
Bottom/Toe 6/22/2021 Partial Approval ALEXANDER ANDREWS
Deputy Grading 6/22/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/23/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/24/2021 Approved ALEXANDER ANDREWS
Deputy Grading 6/25/2021 Approved ALEXANDER ANDREWS
Bottom/Toe 6/28/2021 Approved MANUEL TEJADA
Deputy Grading 6/28/2021 Approved MANUEL TEJADA
Deputy Grading 6/29/2021 Approved ALEXANDER HELFER
Bottom/Toe 7/2/2021 Approved VASIL MIHALEV
Rough 7/2/2021 Approved VASIL MIHALEV
Drainage Devices/Catch Basin 7/6/2021 Not Ready for Inspection ALEXANDER ANDREWS
Drainage Devices/Catch Basin 7/9/2021 Partial Approval ALEXANDER ANDREWS
Approved Compaction Report 7/19/2021 Approved BRIAN MILLER
Drainage Devices/Catch Basin 7/30/2021 No Access for Inspection MANUEL TEJADA
Drainage Devices/Catch Basin 8/2/2021 Partial Approval MANUEL TEJADA
Fill/Backfill 8/2/2021 Partial Approval MANUEL TEJADA
Deputy Grading 8/13/2021 Approved MANUEL TEJADA
Deputy Grading 8/16/2021 Approved MANUEL TEJADA
Drainage Devices/Catch Basin 9/13/2021 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 9/14/2021 Partial Approval TIMOTHY POWELL
Sub-Drain 11/16/2022 Partial Approval MICHAEL TEMPLE
Sub-Drain 11/21/2022 Partial Approval TIMOTHY POWELL
Sub-Drain 12/9/2022 Approved LANNY MERRICK
Approved Compaction Report 2/7/2023 Approved BRIAN MILLER
Final 3/7/2023 Not Ready for Inspection BRIAN MILLER
Final 3/31/2023 Permit Finaled ROBERT PINA