983 S DEWEY AVE 90006
Certificate Information: 983 S DEWEY AVE 90006
- Application / Permit
- 20030-10000-06362
- Plan Check / Job No.
- B20LA20695
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Early Start : GRADING FOR (N) APARTMENT
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/25/2024
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | HERNAN ARREOLA |
| Corrections Issued | 12/16/2020 | HERNAN ARREOLA |
| Quality Review Completed | 12/23/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 3/21/2021 | HERNAN ARREOLA |
| Green Plans Picked Up | 4/15/2021 | APPLICANT |
| Applicant returned to address corrections | 4/23/2021 | HERNAN ARREOLA |
| Building Plans Picked Up | 4/23/2021 | APPLICANT |
| Plan Check Approved | 8/13/2021 | HERNAN ARREOLA |
| Issued | 8/13/2021 | APPLICANT |
| Permit Finaled | 10/24/2024 | JONATHAN HOM |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| Opn space landscape/Water mgmt | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/16/2021 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 7/23/2021 | GRACIELA ACOSTA |
| Building over 3-story or 36-ft | Cleared | 8/4/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/4/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | 2201 N LAKEWOOD BLVD STE D643 LONG BEACH, CA 90815 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/17/2021 | Approved | ALEXANDER HELFER |
| Excavation | 9/2/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 10/19/2021 | Partial Approval | ALEXANDER HELFER |
| Rough | 1/19/2022 | Partial Inspection | LANNY MERRICK |
| Sub-Drain | 1/27/2022 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 10/11/2024 | Partial Inspection | JONATHAN HOM |
| Final | 10/11/2024 | Partial Inspection | JONATHAN HOM |
| Rough | 10/11/2024 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 10/24/2024 | Approved | JONATHAN HOM |
| Final | 10/24/2024 | Permit Finaled | JONATHAN HOM |
| Rough | 10/24/2024 | Approved | JONATHAN HOM |