2816 N SUNDAY TR 90068

Certificate Information: 2816 N SUNDAY TR 90068

Application / Permit
20030-10000-06279
Plan Check / Job No.
B20LA20352
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR REMEDIAL SLOPE REPAIR
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
Permit Finaled on 2/18/2025

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/18/2020 ZAW HAN
Corrections Issued 11/25/2020 ZAW HAN
Applicant returned to address corrections 1/20/2022 GEORGE ALVAREZ
Plan Check Approved 2/3/2022 GEORGE ALVAREZ
Issued 2/14/2022 APPLICANT
Building Plans Picked Up 3/4/2022 APPLICANT
Permit Finaled 2/14/2025 MANUEL TEJADA

Permit Application Clearance Information

Specific Plan Cleared 2/17/2021 LAURA FRAZIN-STEELE
Grading Pre-Inspection Cleared 2/22/2021 PATRICK MISCHLICH
Low Impact Development Cleared 2/23/2021 IDA MEISAMI-FARD

Contact Information

Contractor Alonso Grading And Demolition Inc; Lic. No.: 1022909-C12 1326 EAST 78TH ST      LOS ANGELES, CA 90001
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Carnegie,, Vincent John; Lic. No.: EG1608 P.O. BOX 5444      GLENDALE, CA 912012036

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 2/22/2022 Approved TIMOTHY POWELL
Bottom/Toe 3/3/2022 Corrections Issued MATTHEW JENKINS
Excavation 3/8/2022 Partial Inspection TIMOTHY POWELL
Excavation 3/16/2022 Partial Approval TIMOTHY POWELL
Bottom/Toe 3/23/2022 Partial Approval TIMOTHY POWELL
Fill/Backfill 3/30/2022 Partial Approval TIMOTHY POWELL
Excavation 4/14/2022 Partial Approval LANNY MERRICK
Sub-Drain 4/14/2022 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 4/19/2022 Approved MANUEL TEJADA
Final 4/19/2022 Corrections Issued MANUEL TEJADA
Rough 4/19/2022 Approved MANUEL TEJADA
Approved Compaction Report 5/18/2022 Approved MANUEL TEJADA
Final 2/14/2025 Permit Finaled MANUEL TEJADA