4557 W AMBROSE AVE 90027

Certificate Information: 4557 W AMBROSE AVE 90027

Application / Permit
20030-10000-05751
Plan Check / Job No.
G20LA00225
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR A 4 LOT SUBDIVISION UNDER AA-2017-1445-PMLA-SL. CUT= 480 C.Y FILL= 45 CY EXPORT = 325 CY R&R = 1,100 C.Y
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
Permit Finaled on 10/19/2023

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/26/2020 DAN RYAN EVANGELISTA
Corrections Issued 10/26/2020 DAN RYAN EVANGELISTA
Plan Check Approved 8/9/2021 DAN RYAN EVANGELISTA
Issued 8/19/2021 APPLICANT
Permit Finaled 10/18/2023 ALEXANDER HELFER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/4/2020 ROSA SILVA
Low Impact Development Cleared 3/2/2021 ANDRES COVARRUBIAS
Permit Cleared 3/18/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 3/18/2021 WALLIE JONG
Tract Map conditions Cleared 5/7/2021 KENTON TRINH
Miscellaneous Cleared 8/3/2021 BIJAN ZADEH
Excavation more than 5-ft deep Cleared 8/9/2021 CALOSHA APPROVED

Contact Information

Contractor La Rocca Design; Lic. No.: 779452-B 921 SOUTH SPAULDING AVENUE      LOS ANGELES, CA 90046
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Sahebi,, Mo; Lic. No.: C33508 1330 OLYMPIC BL      SANTA MONICA, CA 90404
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/4/2021 Corrections Issued ALEXANDER HELFER
Bottom/Toe 10/12/2021 Partial Approval ALEXANDER HELFER
Bottom/Toe 10/15/2021 Partial Approval ALEXANDER HELFER
Bottom/Toe 10/21/2021 Partial Approval LANNY MERRICK
Bottom/Toe 10/26/2021 Partial Approval LANNY MERRICK
Approved Compaction Report 11/16/2021 Approved ROBERT HUGHES
Sub-Drain 3/1/2022 Partial Approval ROBERT HUGHES
Sub-Drain 4/4/2022 Partial Approval ROBERT HUGHES
Sub-Drain 4/26/2022 Partial Approval ROBERT HUGHES
Sub-Drain 4/29/2022 Partial Approval ROBERT HUGHES
Sub-Drain 5/9/2022 Partial Approval ROBERT HUGHES
Sub-Drain 6/6/2022 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 9/27/2023 Not Ready for Inspection ALEXANDER HELFER
Approved Compaction Report 10/6/2023 Approved ROBERT HUGHES
Approved Compaction Report 10/18/2023 Approved ALEXANDER HELFER
Bottom/Toe 10/18/2023 Approved ALEXANDER HELFER
Final 10/18/2023 Permit Finaled ALEXANDER HELFER
Rough 10/18/2023 Approved ALEXANDER HELFER