635 W WASHINGTON BLVD 90015
Certificate Information: 635 W WASHINGTON BLVD 90015
- Application / Permit
- 20030-10000-05460
- Plan Check / Job No.
- B20LA18018
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR A NEW CAR DEALERSHIP ON PERMIT 20014-10000-04317
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/3/2023
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | JOE VO |
| Corrections Issued | 11/26/2020 | JOE VO |
| Quality Review Completed | 12/11/2020 | MINYE PAK |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| Applicant returned to address corrections | 4/20/2021 | JOE VO |
| Applicant returned to address corrections | 5/10/2021 | JOE VO |
| Plan Check Approved | 5/10/2021 | JOE VO |
| Plan Check Approved | 5/24/2021 | JOE VO |
| Issued | 6/8/2021 | APPLICANT |
| Permit Finaled | 5/2/2023 | JONATHAN HOM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 1/6/2021 | ALBERT TAM |
| Community Plan Implem. Overlay | Cleared | 2/2/2021 | TORI CHEN |
| Community Plan Implem. Overlay | Cleared | 2/25/2021 | TAIMOUR TANAVOLI |
| Community Plan Implem. Overlay | Cleared | 3/3/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
| Prkng lot landscape/Water mgmt | Cleared | 3/9/2021 | RUBEN VASQUEZ |
| Site Plan review | Cleared | 3/9/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/9/2021 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 3/11/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 3/23/2021 | HELEN JADALI |
| Redevelopment Project Area | Cleared | 3/23/2021 | DAVID URITA |
| Highway dedication | Cleared | 3/30/2021 | SAM NAVID |
| Permit | Cleared | 3/30/2021 | SAM NAVID |
| Work Adjacent to Public Way | Cleared | 5/19/2021 | JOSE RODRIGUEZ |
Contact Information
| Contractor | Bomel Construction Co Inc; Lic. No.: 265409-B | 96 CORPORATE PARK IRVINE, CA 92606 |
| Engineer | Stenzel,, Reinhard Christian; Lic. No.: C56155 | 5681 HIGHLAND AVENUE YORBA LINDA, CA 92886 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/14/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/18/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 6/21/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 6/21/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/22/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 6/23/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 6/23/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/24/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/25/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/28/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 6/29/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 6/30/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 6/30/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 7/1/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 7/2/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 7/6/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/7/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 7/8/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 7/8/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 7/9/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 7/12/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 7/13/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/14/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 7/15/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/16/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 7/19/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/19/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/20/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/21/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/22/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/23/2021 | Approved | ALEXANDER HELFER |
| Rough | 7/26/2021 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 8/16/2021 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 8/25/2021 | Approved | ALEXANDER HELFER |
| Excavation | 5/23/2022 | Partial Inspection | MATTHEW JENKINS |
| Final | 5/2/2023 | Permit Finaled | JONATHAN HOM |
| Special/Order Compliance | 5/2/2023 | Approved | JONATHAN HOM |