2212 W NORWALK AVE 90041
Certificate Information: 2212 W NORWALK AVE 90041
- Application / Permit
- 20030-10000-05382
- Plan Check / Job No.
- B20LA13712
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR THE SMALL LOT SUBDIVISION AND REMOVAL AND RECOMPACTION FOR THE NEW 5 UNITS. "SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO 82846-SL . A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED"
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/23/2024
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | MINA HABIB |
| Corrections Issued | 9/28/2020 | MINA HABIB |
| Quality Review Completed | 10/7/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/17/2021 | MINA HABIB |
| Applicant returned to address corrections | 5/5/2021 | MINA HABIB |
| Applicant returned to address corrections | 6/14/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/9/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/10/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/30/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/7/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/8/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/25/2021 | MINA HABIB |
| Applicant returned to address corrections | 2/10/2022 | MINA HABIB |
| Applicant returned to address corrections | 3/16/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/14/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/19/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/20/2022 | MINA HABIB |
| Applicant returned to address corrections | 7/27/2022 | MINA HABIB |
| Applicant returned to address corrections | 8/9/2022 | MINA HABIB |
| Applicant returned to address corrections | 9/1/2022 | MINA HABIB |
| Applicant returned to address corrections | 11/3/2022 | MINA HABIB |
| Applicant returned to address corrections | 1/27/2023 | MINA HABIB |
| Applicant returned to address corrections | 2/14/2023 | MINA HABIB |
| Applicant returned to address corrections | 3/16/2023 | MINA HABIB |
| Plan Check Approved | 3/24/2023 | MINA HABIB |
| Issued | 8/23/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | WALLIE JONG |
| Miscellaneous | Cleared | 4/27/2021 | ALBERT TAM |
| Miscellaneous | Cleared | 7/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/2/2021 | ANACANY HURTADO |
| Grading Pre-Inspection | Cleared | 7/22/2021 | MINA HABIB |
| Work Adjacent to Public Way | Cleared | 12/15/2022 | KHOUNG LE |
| Excavation more than 5-ft deep | Cleared | 3/16/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 3/16/2023 | MINA HABIB |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Jong,, Hank Hsing-Lian; Lic. No.: C45846 | 11819 GOLDRING ROAD UNIT A ARCADIA, CA 91006 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/2/2024 | Approved | LANNY MERRICK |
| Bottom/Toe | 10/8/2024 | Approved | LANNY MERRICK |
| Excavation | 10/16/2024 | Partial Approval | MICHAEL TEMPLE |
| Rough | 10/21/2024 | Partial Approval | LANNY MERRICK |
| Rough | 10/24/2024 | Partial Approval | LANNY MERRICK |
| Rough | 10/28/2024 | Partial Approval | LANNY MERRICK |
| Approved Compaction Report | 11/18/2024 | Approved | ALEXANDER HELFER |
| Sub-Drain | 1/3/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 4/8/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 5/11/2026 | Not Ready for Inspection | JONATHAN HOM |
| Rough | 5/11/2026 | Partial Inspection | JONATHAN HOM |