4136 E RAYNOL ST 90032

Certificate Information: 4136 E RAYNOL ST 90032

Application / Permit
20030-10000-05245
Plan Check / Job No.
B20LA11663
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site Grading for proposed New SFD
Permit Issued
Issued on 6/9/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/9/2025

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 ZAW HAN
Corrections Issued 9/9/2020 ZAW HAN
Quality Review Completed 9/16/2020 TU HUA
Building Plans Picked Up 9/17/2020 APPLICANT
Applicant returned to address corrections 10/27/2020 ZAW HAN
Applicant returned to address corrections 3/11/2021 ZAW HAN
Applicant returned to address corrections 6/23/2021 ZAW HAN
Applicant returned to address corrections 6/30/2021 ZAW HAN
Plan Check Approved 7/14/2021 ZAW HAN
Issued 6/9/2022 APPLICANT
Permit Finaled 2/7/2025 LANNY MERRICK

Permit Application Clearance Information

"D" conditions Cleared 6/17/2021 JOE LUCKEY
"Q" conditions Cleared 6/17/2021 JOE LUCKEY
ZA Case Cleared 6/17/2021 JOE LUCKEY
ZI Cleared 6/17/2021 JOE LUCKEY
ZI Cleared 6/17/2021 JOE LUCKEY
GPI Written Notices Cleared 6/29/2021 ROBERT HUGHES
Grading Pre-Inspection Cleared 6/29/2021 ROBERT HUGHES
Low Impact Development Cleared 6/29/2021 ANDRES COVARRUBIAS

Contact Information

Contractor Owner-Builder       ,
Engineer Esmaily-Radvar,, Shahrokh; Lic. No.: GE2742 5 HODGENVILLE      IRVINE, CA 92620
Engineer Gabrielson,, Leonard Harrell; Lic. No.: L7886 12 BALMA LANE      PETALUMA, CA 94952
Engineer Pajuhesh,, Jamshid; Lic. No.: S1860 6824 LOUISE AVE      VAN NUYS, CA 91406

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/20/2022 Not Ready for Inspection ROBERT HUGHES
Initial Grading 7/21/2022 Partial Approval ROBERT HUGHES
Deputy Other (see comments) 10/13/2022 Approved ROBERT HUGHES
Sub-Drain 10/17/2022 Partial Approval ROBERT HUGHES
Deputy Grading 11/4/2022 Approved ROBERT HUGHES
Bottom/Toe 12/19/2024 Approved LANNY MERRICK
Final 12/19/2024 Not Ready for Inspection LANNY MERRICK
Rough 12/19/2024 Approved LANNY MERRICK
Special/Order Compliance 12/27/2024 Corrections Issued LANNY MERRICK
Approved Compaction Report 1/27/2025 Approved LANNY MERRICK
Final 2/7/2025 Permit Finaled LANNY MERRICK