Grading for the proposed 6 story 94 UNIT type III-A affordable apartments over 1 story of type I-A commercial, residential amenities, garage and back of house spaces. No basement. Project is 100% affordable.
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
Permit Finaled on 5/22/2023

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 QUAN NGHIEM
Disabled Access Plans Picked Up 1/5/2021 APPLICANT
Corrections Issued 1/22/2021 QUAN NGHIEM
Quality Review Completed 1/22/2021 ALLEN MANALANSAN
Building Plans Picked Up 1/28/2021 APPLICANT
Applicant returned to address corrections 4/1/2021 QUAN NGHIEM
Applicant returned to address corrections 4/6/2021 QUAN NGHIEM
Applicant returned to address corrections 4/7/2021 QUAN NGHIEM
Applicant returned to address corrections 6/18/2021 QUAN NGHIEM
Green Plans Picked Up 6/29/2021 APPLICANT
Plan Check Approved 7/28/2021 QUAN NGHIEM
Issued 9/10/2021 APPLICANT
Permit Finaled 5/19/2023 LANNY MERRICK

Permit Application Clearance Information

Hold Cleared 10/20/2021 JASON SHEETS

Contact Information

Architect Olsen,, Eric H; Lic. No.: C27721 3802 OSTROM AVE      LONG BEACH, CA 90808
Contractor Suffolk Construction Company Inc; Lic. No.: 751099-B 525 MARKET STREET   SUITE 2850    SAN FRANCISCO, CA 94105
Engineer Aden,, Mark D; Lic. No.: S4779 1314 S GRAND BLVD 2-359      SPOKANE, WA 99202
Engineer Luong,, John Tuan; Lic. No.: C65214 8171 INGRAM CIR      WESTMINSTER, CA 92683

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/25/2021 Partial Inspection LANNY MERRICK
Bottom/Toe 1/19/2022 Partial Approval LANNY MERRICK
Bottom/Toe 1/21/2022 Approved LANNY MERRICK
Rough 1/26/2022 Partial Approval LANNY MERRICK
Fill/Backfill 2/1/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 2/7/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 2/10/2022 Not Ready for Inspection LANNY MERRICK
Approved Compaction Report 2/11/2022 Approved ROBERT HUGHES
Bottom/Toe 2/15/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 2/16/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 2/17/2022 Partial Approval LANNY MERRICK
Bottom/Toe 3/1/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 3/7/2022 Partial Inspection LANNY MERRICK
Drainage Devices/Catch Basin 11/22/2022 Partial Approval MATTHEW JENKINS
Bottom/Toe 4/26/2023 Approved LANNY MERRICK
Final 4/26/2023 Not Ready for Inspection LANNY MERRICK
Rough 4/26/2023 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 4/28/2023 Partial Approval ROBERT HUGHES
Excavation 4/28/2023 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 5/9/2023 Partial Approval JONATHAN HOM
Final 5/19/2023 Permit Finaled LANNY MERRICK
Rough 5/19/2023 Approved LANNY MERRICK