18825 W CALVERT ST 91335

Certificate Information: 18825 W CALVERT ST 91335

Application / Permit
20030-10000-04876
Plan Check / Job No.
B20LA16179
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR NEW SYNAGOGUE - PER ZA - 2019-1043-CU
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
Issued on 4/8/2022

Permit Application Status History

Submitted 10/5/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 JOHNNY WU
Corrections Issued 10/30/2020 JOHNNY WU
Quality Review Completed 11/10/2020 TIEN JEN WANG
Building Plans Picked Up 4/11/2021 APPLICANT
Applicant returned to address corrections 12/3/2021 JOHNNY WU
Applicant returned to address corrections 12/8/2021 JOHNNY WU
Applicant returned to address corrections 12/10/2021 JOHNNY WU
Plan Check Approved 12/29/2021 JOHNNY WU
Issued 4/8/2022 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 12/8/2021 JOHNNY WU
GPI Written Notices Cleared 12/10/2021 JOHNNY WU
GPI Written Notices Cleared 12/29/2021 JOHNNY WU

Contact Information

Contractor Ace General Contracting Inc; Lic. No.: 1060906-B 6924 CANBY AVENUE #120      RESEDA, CA 91335
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Landscape Architect Mc, Eowen, Susan E; Lic. No.: LA2180 19197 GOLDEN VALLEY RD 924      SANTA CLARITA, CA 91387

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 6/24/2022 Partial Inspection LANNY MERRICK
Bottom/Toe 7/5/2022 No Access for Inspection VASIL MIHALEV
Fill/Backfill 7/6/2022 Approved VASIL MIHALEV
Approved Compaction Report 8/17/2022 Approved LANNY MERRICK
Bottom/Toe 9/2/2022 Partial Approval LANNY MERRICK
Final 9/2/2022 Not Ready for Inspection LANNY MERRICK
Rough 9/2/2022 Partial Approval LANNY MERRICK
Bottom/Toe 12/28/2023 Not Ready for Inspection ROBERT PINA
Final 12/28/2023 Not Ready for Inspection ROBERT PINA
Rough 12/28/2023 Not Ready for Inspection ROBERT PINA
Drainage Devices/Catch Basin 6/17/2025 Partial Approval MANUEL TEJADA
Rough 10/6/2025 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 12/18/2025 Partial Approval MANUEL TEJADA
Bottom/Toe 3/4/2026 Not Ready for Inspection MANUEL TEJADA
Final 3/4/2026 Not Ready for Inspection MANUEL TEJADA
Rough 3/4/2026 Not Ready for Inspection MANUEL TEJADA