1421 W ADAMS BLVD 90007
Certificate Information: 1421 W ADAMS BLVD 90007
- Application / Permit
- 20030-10000-04724
- Plan Check / Job No.
- B20LA04825
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for proposed Apartment excavation
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/16/2022
Permit Application Status History
Submitted | 3/10/2020 | APPLICANT |
Assigned to Plan Check Engineer | 3/19/2020 | HERNAN ARREOLA |
Corrections Issued | 3/26/2020 | HERNAN ARREOLA |
Quality Review Completed | 4/6/2020 | BILL STUTSMAN |
Building Plans Picked Up | 4/8/2020 | APPLICANT |
Applicant returned to address corrections | 7/27/2020 | HERNAN ARREOLA |
Plan Check Approved | 10/7/2020 | HERNAN ARREOLA |
Issued | 10/7/2020 | APPLICANT |
Permit Finaled | 6/16/2022 | ALEXANDER HELFER |
Permit Application Clearance Information
Community Plan Implem. Overlay | Cleared | 9/1/2020 | HELEN JADALI |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Nazemi,, Hassan Steve; Lic. No.: C44100 | 275 CENTENNIAL WAY 205 TUSTIN, CA 92780 |
Inspector Information
JONATHAN HOM, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Grading | 10/13/2020 | Approved | ALEXANDER HELFER |
Excavation | 10/17/2020 | Not Ready for Inspection | VASIL MIHALEV |
Initial Grading | 10/17/2020 | Approved | VASIL MIHALEV |
Deputy Grading | 10/19/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 10/20/2020 | Approved | VASIL MIHALEV |
Deputy Grading | 10/21/2020 | Approved | VASIL MIHALEV |
Deputy Grading | 10/22/2020 | Approved | VASIL MIHALEV |
Deputy Grading | 10/23/2020 | Conditional Approval | ALEXANDER HELFER |
Deputy Grading | 10/27/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 10/28/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 10/29/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 10/30/2020 | Approved | ROBERT HUGHES |
Deputy Grading | 11/2/2020 | Approved | ROBERT HUGHES |
Deputy Grading | 11/4/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 11/5/2020 | Approved | ALEXANDER HELFER |
Deputy Grading | 11/6/2020 | Approved | ALEXANDER HELFER |
Sub-Drain | 11/18/2020 | Partial Approval | ALEXANDER HELFER |
Sub-Drain | 12/2/2020 | Partial Approval | ALEXANDER HELFER |
Bottom/Toe | 2/10/2021 | Not Ready for Inspection | ALEXANDER HELFER |
Sub-Drain | 2/10/2021 | Approved | ALEXANDER HELFER |
Sub-Drain | 3/12/2021 | Partial Approval | ALEXANDER HELFER |
Drainage Devices/Catch Basin | 4/13/2022 | Partial Approval | MATTHEW JENKINS |
Bottom/Toe | 6/16/2022 | Approved | ALEXANDER HELFER |
Final | 6/16/2022 | Permit Finaled | ALEXANDER HELFER |
Rough | 6/16/2022 | Approved | ALEXANDER HELFER |