6300 W FOREST LAWN DR 90068

Certificate Information: 6300 W FOREST LAWN DR 90068

Application / Permit
20030-10000-04350
Plan Check / Job No.
B20LA14669
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
Grading for construction of garden, retaining walls, block walls
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
Permit Finaled on 8/20/2025

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 VU NGUYEN
Corrections Issued 9/30/2020 VU NGUYEN
Quality Review Completed 10/7/2020 RODOLFO ARIAS
Applicant returned to address corrections 8/19/2021 VU NGUYEN
Plan Check Approved 9/30/2021 VU NGUYEN
Issued 1/26/2022 APPLICANT
Building Plans Picked Up 2/7/2022 APPLICANT
Permit Finaled 8/19/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

CPC Cleared 12/11/2020 DENZEL HENDERSON
CPC Cleared 12/11/2020 DENZEL HENDERSON
Grading in hillside Cleared 12/11/2020 DENZEL HENDERSON
ZA Case Cleared 12/11/2020 DENZEL HENDERSON
ZA Case Cleared 12/11/2020 DENZEL HENDERSON
ZA Case Cleared 12/11/2020 DENZEL HENDERSON
Low Impact Development Cleared 12/16/2020 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 12/22/2020 ROSA SILVA
Roof/Waste drainage to street Cleared 1/5/2021 SAM NAVID
ZA Case Cleared 1/6/2021 DENZEL HENDERSON
Excavation more than 5-ft deep Cleared 8/19/2021 CALOSHA APPROVED
CPC Cleared 8/31/2021 ERIN STRELICH
Grading Pre-Inspection Cleared 9/28/2021 VU NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LANNY MERRICK, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 10/19/2022 Partial Approval ROBERT HUGHES
Rough 11/7/2023 Partial Approval RUSSELL BONVOULOIR
Excavation 3/26/2024 Approved ALEXANDER HELFER
Excavation 4/1/2024 Approved ALEXANDER HELFER
Sub-Drain 4/5/2024 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 11/19/2024 Approved ALEXANDER HELFER
Rough 5/23/2025 Partial Approval ROBERT PINA
Irrigation/Landscape 5/28/2025 Partial Inspection RUSSELL BONVOULOIR
Bottom/Toe 6/23/2025 Approved RUSSELL BONVOULOIR
Final 6/23/2025 Corrections Issued RUSSELL BONVOULOIR
Rough 6/23/2025 Approved RUSSELL BONVOULOIR
Approved Compaction Report 8/19/2025 Approved RUSSELL BONVOULOIR
Final 8/19/2025 Permit Finaled RUSSELL BONVOULOIR