15200 W BLEDSOE ST 91342
Certificate Information: 15200 W BLEDSOE ST 91342
- Application / Permit
- 20030-10000-03521
- Plan Check / Job No.
- B20LA12031
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING - REMOVE AND RECOMPACT, DRAINAGE PLAN FOR NEW BUILDING PAD.
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- Issued on 9/28/2021
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Application Withdrawn | 8/4/2020 | APPLICANT |
| Re-Activate Applicaton | 8/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | SAM CHANG |
| Corrections Issued | 9/14/2020 | SAM CHANG |
| Quality Review Completed | 9/29/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 10/26/2020 | SAM CHANG |
| Applicant returned to address corrections | 10/27/2020 | SAM CHANG |
| Applicant returned to address corrections | 11/17/2020 | SAM CHANG |
| Applicant returned to address corrections | 12/2/2020 | SAM CHANG |
| Green Plans Picked Up | 4/23/2021 | APPLICANT |
| Applicant returned to address corrections | 7/7/2021 | SAM CHANG |
| Plan Check Approved | 9/3/2021 | SAM CHANG |
| Issued | 9/28/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 10/7/2021 | APPLICANT |
| Building Plans Picked Up | 1/11/2022 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/19/2021 | SAM CHANG |
| Work Adjacent to Public Way | Cleared | 7/28/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Xebec Building Company Inc; Lic. No.: 600621-B | 3010 OLD RANCH PARKWAY STE 480 SEAL BEACH, CA 90740 |
| Engineer | Robles,, Eric; Lic. No.: C89866 | 2748 WASHINGTON AVE EL MONTE, CA 91733 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/1/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 1/26/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 1/27/2022 | No Access for Inspection | BRIAN MILLER |
| Bottom/Toe | 1/31/2022 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 1/31/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 2/1/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/2/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/3/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 2/4/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/4/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/7/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 2/8/2022 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 2/8/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/9/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 2/10/2022 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 2/10/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/11/2022 | Approved | MANUEL TEJADA |
| Bottom/Toe | 2/16/2022 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 2/17/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/18/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/23/2022 | Approved | BRIAN MILLER |
| Special/Order Compliance | 2/23/2022 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 2/24/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 2/25/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 3/1/2022 | Approved | PATRICK MISCHLICH |
| Deputy Grading | 3/2/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 3/3/2022 | Approved | MANUEL TEJADA |
| Deputy Grading | 3/4/2022 | No Access for Inspection | MANUEL TEJADA |
| Deputy Grading | 3/7/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/8/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/9/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/10/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/11/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/14/2022 | Approved | BRIAN MILLER |
| Special/Order Compliance | 3/14/2022 | Partial Inspection | BRIAN MILLER |
| Deputy Grading | 3/15/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 3/16/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 3/17/2022 | Approved | BRIAN MILLER |
| Deputy Grading | 3/18/2022 | Approved | BRIAN MILLER |
| Approved Compaction Report | 4/5/2022 | Corrections Issued | VASIL MIHALEV |
| Approved Compaction Report | 4/15/2022 | Approved | VASIL MIHALEV |
| Special/Order Compliance | 4/29/2022 | Partial Inspection | LANNY MERRICK |
| Deputy Grading | 5/3/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 5/4/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 5/5/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 5/6/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 6/2/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 6/3/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 11/1/2022 | Conditional Approval | LANNY MERRICK |
| Drainage Devices/Catch Basin | 1/26/2024 | Partial Inspection | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 4/17/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 6/13/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 6/13/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 6/17/2024 | Partial Approval | CHARLES POWELL |
| Excavation | 6/17/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 6/24/2024 | Partial Approval | CHARLES POWELL |
| Excavation | 6/24/2024 | Not Ready for Inspection | CHARLES POWELL |
| Drainage Devices/Catch Basin | 7/2/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 7/11/2024 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/16/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 7/24/2024 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/31/2024 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 11/5/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 1/6/2025 | Partial Approval | CHARLES POWELL |
| Special/Order Compliance | 9/10/2025 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SWPPP-Const. Storm Water | 11/14/2025 | Completed | GERMAN RODRIGUEZ MENDOZA |