240 N MADISON AVE 90004
Certificate Information: 240 N MADISON AVE 90004
- Application / Permit
- 20030-10000-02899
- Plan Check / Job No.
- B20LA10087
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR THE PROPOSED CHARTER SCHOOL.
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/2/2022
Permit Application Status History
| Submitted | 7/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | YOUNG KIM |
| Corrections Issued | 7/13/2020 | YOUNG KIM |
| Quality Review Completed | 7/15/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 8/29/2020 | YOUNG KIM |
| Plan Check Approved | 3/5/2021 | YOUNG KIM |
| Issued | 3/17/2021 | APPLICANT |
| Building Plans Picked Up | 4/7/2021 | APPLICANT |
| Permit Finaled | 5/2/2022 | ROBERT HUGHES |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/13/2021 | KENTON TRINH |
Contact Information
| Architect | Csda, Design Group; Lic. No.: C35165 | 889 N. DOUGLAS ST. 100 EL SEGUNDO, CA 90245 |
| Contractor | Cattrac Construction Inc; Lic. No.: 410347-A | 15030 SLOVER AVENUE FONTANA, CA 92337 |
| Engineer | Grossman, & Speer Associates, Inc.; Lic. No.: S6228 | 529 HAHN AVE STE #200 GLENDALE, CA 91203 |
| Engineer | Vca, Engineering Inc.; Lic. No.: C36079 | 1041 S GARFIELD AVE STE #210 ALHAMBRA, CA 91801 |
| Landscape Architect | Brightview, Design Group; Lic. No.: LA1846 | 1715 18TH ST. SANTA MONICA, CA 90404 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/18/2021 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 3/26/2021 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 4/5/2021 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 4/9/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 4/9/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 4/13/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 4/20/2021 | Partial Approval | ROBERT HUGHES |
| Approved Compaction Report | 5/11/2021 | Approved | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 5/18/2021 | Partial Approval | ROBERT HUGHES |
| Irrigation/Landscape | 5/18/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 5/18/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 5/18/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 5/19/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 5/19/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Bottom/Toe | 8/4/2021 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/5/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 8/6/2021 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 12/20/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 12/22/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 1/12/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 1/19/2022 | Approved | ALEXANDER HELFER |
| Sub-Drain | 1/25/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 2/9/2022 | Not Ready for Inspection | LANNY MERRICK |
| Drainage Devices/Catch Basin | 2/14/2022 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 2/17/2022 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 4/7/2022 | Approved | ALEXANDER HELFER |
| Final | 4/20/2022 | Corrections Issued | MATTHEW JENKINS |
| Rough | 4/20/2022 | Approved | MATTHEW JENKINS |
| Final | 5/2/2022 | Permit Finaled | ROBERT HUGHES |