6065 N HAZELHURST PL 91606
Certificate Information: 6065 N HAZELHURST PL 91606
- Application / Permit
- 20030-10000-02893
- Plan Check / Job No.
- G20LA00119
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ROUGH GRADING FOR 5 LOT SUBDIVISION UNDER VESTING TENTATIVE TRACT MAP NO. 82621-SL. CUT = 1,400 CY.; FILL = CY.; R&R =1,400 CY
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/28/2023
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2020 | DAN RYAN EVANGELISTA |
| Corrections Issued | 6/15/2020 | DAN RYAN EVANGELISTA |
| Applicant returned to address corrections | 10/21/2020 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 12/21/2020 | DAN RYAN EVANGELISTA |
| Issued | 12/21/2020 | APPLICANT |
| Permit Finaled | 7/27/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 8/21/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | ADRIAN CASTRO |
| Stormwater Pollution Mitigatn | Cleared | 10/7/2020 | ANDRES COVARRUBIAS |
| Tract Map conditions | Cleared | 10/7/2020 | JASON CHAN |
| Permit | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 12/9/2020 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazemi,, Hassan Steve; Lic. No.: C44100 | 275 CENTENNIAL WAY 205 TUSTIN, CA 92780 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 1/13/2021 | Partial Approval | TIMOTHY POWELL |
| Initial Grading | 1/13/2021 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 1/20/2021 | Approved | VASIL MIHALEV |
| Approved Compaction Report | 2/17/2021 | Approved | BRIAN MILLER |
| Final | 7/27/2023 | Permit Finaled | MANUEL TEJADA |
| Rough | 7/27/2023 | Approved | MANUEL TEJADA |