6329 N CLYBOURN AVE 91606
Certificate Information: 6329 N CLYBOURN AVE 91606
- Application / Permit
- 20030-10000-02522
- Plan Check / Job No.
- B20LA09095
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ROUGH GRADING (LARGE SITE) FOR NEW 103 UNIT HOUSING PROJECT<<ref.19010-10000-02143>>
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/16/2023
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | DEAN LEE |
| Corrections Issued | 6/26/2020 | DEAN LEE |
| Quality Review Completed | 7/10/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 7/14/2020 | APPLICANT |
| Applicant returned to address corrections | 12/15/2020 | DEAN LEE |
| Applicant returned to address corrections | 12/22/2020 | DEAN LEE |
| Plan Check Approved | 12/23/2020 | DEAN LEE |
| Issued | 12/23/2020 | APPLICANT |
| Permit Finaled-Status Void | 4/28/2023 | MANUEL TEJADA |
| Re-Activate Permit | 6/15/2023 | MANUEL TEJADA |
| Permit Finaled | 6/15/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 1/15/2020 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 10/4/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | MIKE KOUYOUMDJIAN |
Contact Information
| Contractor | Bernards Builders Inc; Lic. No.: 977134-B | 555 FIRST ST SAN FERNANDO, CA 91340 |
| Engineer | Derkalousdian,, Hrair Harry; Lic. No.: C79694 | 3622 VIRGINIA STREET GLENDALE, CA 91214 |
| Engineer | Powers,, Brian Frederick; Lic. No.: C75902 | 2090 WEST 31ST STREET LOS ANGELES, CA 90018 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/17/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Initial Grading | 3/19/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 4/20/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 4/21/2021 | Approved | PATRICK MISCHLICH |
| Deputy Grading | 4/22/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 4/23/2021 | Approved | ALEXANDER ANDREWS |
| Bottom/Toe | 4/26/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 4/26/2021 | Approved | ALEXANDER HELFER |
| Excavation | 4/26/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 4/27/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 4/29/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 5/3/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/4/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/5/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/6/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 5/7/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 5/7/2021 | No Access for Inspection | ALEXANDER HELFER |
| Sub-Drain | 5/11/2021 | Approved | ALEXANDER HELFER |
| Rough | 1/23/2023 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 4/17/2023 | Approved | ROBERT PINA |
| Final | 4/17/2023 | Partial Approval | ROBERT PINA |
| Rough | 4/17/2023 | Approved | ROBERT PINA |
| Final | 4/28/2023 | Conditional Approval | MANUEL TEJADA |
| Approved Compaction Report | 6/15/2023 | Approved | MANUEL TEJADA |
| Final | 6/15/2023 | Permit Finaled | MANUEL TEJADA |