341 S HARVARD BLVD 1-10 90020
Certificate Information: 341 S HARVARD BLVD 1-10 90020
- Application / Permit
- 20030-10000-02510
- Plan Check / Job No.
- B20LA09052
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- BACKFILL OF BUILDING RETAINING WALL APPROX 15 LINEAR FEET. CUT 46.46 C.Y. , FILL 18.32 CY, EXPORT 30.22 CY, IMPORT 0 CY. BUILDING RETAINING WALL UNDER PERMIT# 16014-10003-02955
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/22/2022
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | CATHERINE CHEN |
| Corrections Issued | 10/29/2020 | CATHERINE CHEN |
| Plan Check Approved | 12/30/2020 | CATHERINE CHEN |
| Issued | 12/30/2020 | APPLICANT |
| Permit Finaled | 2/18/2022 | ALEXANDER HELFER |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 10/16/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | 520 SOUTH GRAND AVENUE STE 360 LOS ANGELES, CA 90071 |
| Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
| Engineer | Noorzay,, Maihan; Lic. No.: GE3085 | 16817 RAINY VALE AVE RIVERSIDE, CA 92503 |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/22/2021 | Approved | ALEXANDER HELFER |
| Rough | 5/10/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 7/1/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 7/1/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Bottom/Toe | 10/1/2021 | Corrections Issued | ROBERT HUGHES |
| Final | 10/1/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 10/18/2021 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 1/27/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Final | 1/27/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Approved Compaction Report | 1/31/2022 | Not Ready for Inspection | LANNY MERRICK |
| Fill/Backfill | 1/31/2022 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 1/31/2022 | Approved | LANNY MERRICK |
| Bottom/Toe | 2/18/2022 | Approved | ALEXANDER HELFER |
| Final | 2/18/2022 | Permit Finaled | ALEXANDER HELFER |