1010 S KENMORE AVE 90006
Certificate Information: 1010 S KENMORE AVE 90006
- Application / Permit
- 20030-10000-02376
- Plan Check / Job No.
- B20LA08448
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR NEW 7 STORY APARTMENT BUILDING WITH SUB PARKING
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Metro
- Current Status
- Issued on 7/7/2020
Permit Application Status History
| Plan Check Approved | 7/6/2020 | MICHAEL PEREZ |
| Issued | 7/7/2020 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A R C.City; Lic. No.: 1050930-B | 5500 HOLLYWOOD BLVD STE 306 LOS ANGELES, CA 90028 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/14/2020 | Approved | VASIL MIHALEV |
| Bottom/Toe | 9/11/2020 | Partial Approval | ALEXANDER HELFER |
| Excavation | 9/11/2020 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 9/15/2020 | Partial Approval | ALEXANDER HELFER |
| Rough | 9/15/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Excavation | 9/21/2020 | Approved | VASIL MIHALEV |
| Initial Grading | 9/21/2020 | Approved | VASIL MIHALEV |
| Excavation | 9/25/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 9/25/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Approved Compaction Report | 10/19/2020 | Approved | ALEXANDER HELFER |
| Excavation | 10/29/2020 | Partial Approval | ALEXANDER HELFER |
| Initial Grading | 10/29/2020 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 11/12/2020 | Approved | ALEXANDER HELFER |
| Sub-Drain | 11/12/2020 | Partial Approval | ALEXANDER HELFER |
| Sub-Drain | 11/18/2020 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 11/20/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 11/20/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 11/24/2020 | Approved | VASIL MIHALEV |
| Sub-Drain | 12/8/2020 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 1/11/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 1/28/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 2/2/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 2/12/2021 | Approved | ALEXANDER HELFER |
| Final | 2/12/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 2/12/2021 | Not Ready for Inspection | ALEXANDER HELFER |