283 W IMPERIAL HWY 90061

Certificate Information: 283 W IMPERIAL HWY 90061

Application / Permit
20030-10000-02319
Plan Check / Job No.
B20LA08290
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
SITE GRADING TO REMOVE AND RECOMPACT FOR NEW APARTMENT BUILDING
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
Permit Finaled on 12/29/2023

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 MICHAEL PEREZ
Corrections Issued 5/26/2020 MICHAEL PEREZ
Plan Check Approved 7/14/2020 MICHAEL PEREZ
Issued 7/15/2020 APPLICANT
Permit Finaled 12/28/2023 ALEXANDER HELFER

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 5/14/2020 HELEN JADALI
Miscellaneous Cleared 5/15/2020 ANNA VIDAL
Miscellaneous Cleared 5/15/2020 ANNA VIDAL
Redevelopment Project Area Cleared 5/15/2020 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 5/19/2020 BOK GOH
Work Adjacent to Public Way Cleared 6/29/2020 ROSA SILVA

Contact Information

Contractor Geis Construction West Inc; Lic. No.: 954373-B 10020 AURORA HUDSON ROAD      STREETSBORO, OH 44241
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Krief,, Dan Dov; Lic. No.: C76041 1166 S POINT VIEW STREET      LOS ANGELES, CA 90035

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/22/2020 Approved VASIL MIHALEV
Bottom/Toe 7/28/2020 Approved ALEXANDER HELFER
Excavation 7/30/2020 Partial Approval ALEXANDER HELFER
Excavation 8/4/2020 Approved ALEXANDER HELFER
Approved Compaction Report 8/19/2020 Approved ALEXANDER HELFER
Deputy Grading 8/21/2020 Approved PATRICK MISCHLICH
Excavation 9/1/2020 Approved ALEXANDER HELFER
Final 5/2/2023 Not Ready for Inspection JONATHAN HOM
Rough 5/2/2023 Partial Inspection JONATHAN HOM
Final 12/5/2023 Partial Inspection JONATHAN HOM
Rough 12/5/2023 Partial Inspection JONATHAN HOM
Final 12/19/2023 Partial Inspection JONATHAN HOM
Rough 12/19/2023 Approved JONATHAN HOM
Final 12/28/2023 Permit Finaled ALEXANDER HELFER