3240 N IREDELL LANE 91604

Certificate Information: 3240 N IREDELL LANE 91604

Application / Permit
20030-10000-02239
Plan Check / Job No.
G20LA00098
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
INSTALLATION OF SLOPE STABILIZATION PILES AND SLIDE AREA REPAIR, PER SOILS ENGINEER RECOMMENDATIONS. CUT= 5 CY.; FILL= 160 CY.
Permit Issued
Issued on 7/30/2020
Issuing Office
Current Status
Permit Finaled on 6/7/2022

Permit Application Status History

Submitted 5/4/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 ROCIO DURAN
Corrections Issued 5/21/2020 ROCIO DURAN
Plan Check Approved 7/30/2020 ROCIO DURAN
Issued 7/30/2020 APPLICANT
Permit Finaled 6/6/2022 MANUEL TEJADA

Permit Application Clearance Information

Specific Plan Cleared 6/16/2020 LOUIS ORTEGA
Excavation more than 5-ft deep Cleared 7/30/2020 CALOSHA APPROVED
Grading Pre-Inspection Cleared 7/30/2020 ROCIO DURAN

Contact Information

Architect Rigo, De Righi, Fabio N; Lic. No.: C27735 226 S BEVERLY DRIVE #220      BEVERLY HILLS, CA 90212
Contractor Albino Construction Inc; Lic. No.: 477121-B 12568 W WASHINGTON BLVD   SUITE 200    LOS ANGELES, CA 90066
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 8/24/2020 Partial Approval TIMOTHY POWELL
Excavation 8/24/2020 Partial Approval TIMOTHY POWELL
Final 8/24/2020 Not Ready for Inspection TIMOTHY POWELL
Rough 8/24/2020 Partial Approval TIMOTHY POWELL
Bottom/Toe 9/11/2020 Not Ready for Inspection TIMOTHY POWELL
Sub-Drain 9/28/2020 Partial Inspection TIMOTHY POWELL
Bottom/Toe 10/1/2020 Not Ready for Inspection TIMOTHY POWELL
Bottom/Toe 10/9/2020 Partial Inspection TIMOTHY POWELL
Bottom/Toe 10/22/2020 Partial Approval TIMOTHY POWELL
Sub-Drain 10/30/2020 Partial Approval TIMOTHY POWELL
Sub-Drain 11/12/2020 Partial Approval TIMOTHY POWELL
Approved Compaction Report 1/18/2022 Approved TIMOTHY POWELL
Approved Compaction Report 6/6/2022 Approved MANUEL TEJADA
Bottom/Toe 6/6/2022 Approved MANUEL TEJADA
Final 6/6/2022 Permit Finaled MANUEL TEJADA