1630 N SCHRADER BLVD 90028

Certificate Information: 1630 N SCHRADER BLVD 90028

Application / Permit
20030-10000-02124
Plan Check / Job No.
B20LA07543
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading permit for Proposed Apartment building
Permit Issued
Issued on 12/18/2020
Issuing Office
Current Status
Permit Finaled on 2/27/2023

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 HERNAN ARREOLA
Corrections Issued 6/11/2020 HERNAN ARREOLA
Quality Review Completed 7/2/2020 MINYE PAK
Building Plans Picked Up 7/8/2020 APPLICANT
Plan Check Approved 12/18/2020 HERNAN ARREOLA
Issued 12/18/2020 APPLICANT
Permit Finaled 2/27/2023 ALEXANDER HELFER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/5/2020 WALLIE JONG

Contact Information

Contractor Benchmark Contractors Inc; Lic. No.: 462263-B 3330 OCEAN PARK BLVD      SANTA MONICA, CA 90405
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/8/2021 Approved ALEXANDER HELFER
Excavation 2/3/2021 Approved VASIL MIHALEV
Excavation 3/1/2021 Approved VASIL MIHALEV
Sub-Drain 3/1/2021 Not Ready for Inspection VASIL MIHALEV
Drainage Devices/Catch Basin 3/2/2021 Approved VASIL MIHALEV
Excavation 3/2/2021 Partial Approval VASIL MIHALEV
Excavation 3/3/2021 Approved VASIL MIHALEV
Sub-Drain 3/3/2021 Not Ready for Inspection VASIL MIHALEV
Excavation 3/23/2021 Partial Approval VASIL MIHALEV
Bottom/Toe 3/31/2021 Approved VASIL MIHALEV
Fill/Backfill 4/1/2021 Approved VASIL MIHALEV
Deputy Grading 4/6/2021 Approved VASIL MIHALEV
Fill/Backfill 4/6/2021 Not Ready for Inspection VASIL MIHALEV
Deputy Grading 4/7/2021 Approved VASIL MIHALEV
Deputy Grading 4/8/2021 Approved VASIL MIHALEV
Deputy Grading 4/9/2021 Approved VASIL MIHALEV
Deputy Grading 4/15/2021 Approved VASIL MIHALEV
Deputy Grading 4/16/2021 Approved VASIL MIHALEV
Fill/Backfill 4/21/2021 Approved VASIL MIHALEV
Fill/Backfill 5/7/2021 Approved VASIL MIHALEV
Sub-Drain 5/26/2021 Partial Approval ALEXANDER HELFER
Approved Compaction Report 6/17/2021 Approved ROBERT HUGHES
Approved Compaction Report 7/9/2021 Not Ready for Inspection VASIL MIHALEV
Excavation 7/12/2021 Approved VASIL MIHALEV
Sub-Drain 11/9/2021 Not Ready for Inspection VASIL MIHALEV
Final 1/13/2023 Not Ready for Inspection JONATHAN HOM
Rough 1/13/2023 Not Ready for Inspection JONATHAN HOM
Final 2/24/2023 Partial Inspection ALEXANDER HELFER
Rough 2/24/2023 Approved ALEXANDER HELFER