11845 W VOSE ST 91605

Certificate Information: 11845 W VOSE ST 91605

Application / Permit
20030-10000-02021
Plan Check / Job No.
B20LA07121
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
SITE GRADIGN WORK FOR TI TO EXISTING WAREHOUSE. BUIDING STRUCTURE INSIDE EXISTING WAREHOUSE. GROUNDWATER REMEDIATION SYSTEM, TREATMENT SYSTEM, GENERAL SITE IMPROVEMENTS.
Permit Issued
Issued on 12/8/2020
Issuing Office
Current Status
Permit Finaled on 9/29/2022

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 JOE VO
Plans on Hold 5/26/2020 JOE VO
Hold Released 6/1/2020 JOE VO
Corrections Issued 6/1/2020 JOE VO
Quality Review Completed 7/14/2020 MINYE PAK
Plan Check Approved 11/23/2020 JOE VO
Issued 12/8/2020 APPLICANT
Building Plans Picked Up 12/9/2020 APPLICANT
Permit Finaled 9/28/2022 MANUEL TEJADA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/23/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 10/21/2020 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 11/2/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor American Integrated Services Inc; Lic. No.: 757133-B PO BOX 92316      LONG BEACH, CA 90809
Engineer Blanc,, Anthony; Lic. No.: GE2615 17187 BLUFF VISTA CT      RIVERSIDE, CA 92503

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/16/2020 Approved TIMOTHY POWELL
Bottom/Toe 2/11/2021 Partial Approval TIMOTHY POWELL
Bottom/Toe 3/4/2021 Not Ready for Inspection TIMOTHY POWELL
Bottom/Toe 4/26/2021 Approved ALEXANDER HELFER
Excavation 4/30/2021 Approved ALEXANDER HELFER
Bottom/Toe 5/24/2021 Partial Approval ALEXANDER HELFER
Excavation 5/25/2021 Not Ready for Inspection ALEXANDER HELFER
Excavation 5/27/2021 Approved ALEXANDER HELFER
Excavation 6/2/2021 Approved ALEXANDER HELFER
Excavation 6/8/2021 Partial Approval KIRK LINKLATER
Approved Compaction Report 6/25/2021 Approved TIMOTHY POWELL
Bottom/Toe 7/2/2021 Approved ALEXANDER HELFER
Approved Compaction Report 8/11/2022 Corrections Issued MANUEL TEJADA
Approved Compaction Report 9/23/2022 Approved MANUEL TEJADA
Final 9/28/2022 Permit Finaled MANUEL TEJADA
Rough 9/28/2022 Approved MANUEL TEJADA