3101 W EXPOSITION BLVD 90018
Certificate Information: 3101 W EXPOSITION BLVD 90018
- Application / Permit
- 20030-10000-01688
- Plan Check / Job No.
- B20LA05499
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING PERMIT FOR SITE GRADING AND SUBTERANEAN PARKING STRUCTURE UNDER THE PERMIT# 19010-10000-02837. (PHASE I)
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/10/2021
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | QUAN NGHIEM |
| Corrections Issued | 4/29/2020 | QUAN NGHIEM |
| Quality Review Completed | 5/5/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 7/21/2020 | QUAN NGHIEM |
| Plan Check Approved | 8/5/2020 | QUAN NGHIEM |
| Issued | 8/5/2020 | APPLICANT |
| Building Plans Picked Up | 8/6/2020 | APPLICANT |
| Permit Finaled | 3/9/2021 | ALEXANDER HELFER |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | CECILIO NAVARRO |
| Work Adjacent to Public Way | Cleared | 7/23/2020 | QUAN NGHIEM |
Contact Information
| Architect | Swartz,, David Louis; Lic. No.: C19729 | 1437 4TH STREET SUITE 400 SANTA MONICA, CA 90401 |
| Contractor | Essey Construction Company Inc; Lic. No.: 566045-B | 10801 NATIONAL BOULEVARD #345 LOS ANGELES, CA 90064 |
| Engineer | Breaks,, Matthew Calvin; Lic. No.: S6028 | 5056 TUJUNGA AVE APT 17 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Risha,, Janah Adib; Lic. No.: C46811 | 410 EAST CYPRESS AVE BURBANK, CA 91501 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drainage Devices/Catch Basin | 8/6/2020 | Approved | ALEXANDER HELFER |
| Excavation | 8/6/2020 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 8/6/2020 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 8/6/2020 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 8/6/2020 | Approved | ALEXANDER HELFER |
| Sub-Drain | 8/6/2020 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 8/17/2020 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 8/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 8/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 8/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 8/31/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 8/31/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 9/8/2020 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 9/8/2020 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 9/18/2020 | Approved | VASIL MIHALEV |
| Drainage Devices/Catch Basin | 9/25/2020 | Approved | VASIL MIHALEV |
| Sub-Drain | 9/25/2020 | Approved | VASIL MIHALEV |
| Bottom/Toe | 10/7/2020 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 10/16/2020 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 11/5/2020 | Partial Approval | ALEXANDER HELFER |
| Final | 3/9/2021 | Permit Finaled | ALEXANDER HELFER |