1316-1322 N DOUGLAS ST 90026
Certificate Information: 1316-1322 N DOUGLAS ST 90026
- Application / Permit
- 20030-10000-01201
- Plan Check / Job No.
- G20LA00052
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR 10 LOT SUBDIVISION. CUT = 2,545 CY.; FILL = 115 CY; R&R = 1,425 CY.; EXPORT = 2145 CY 1 OF 3 BF 180048 APPROVED FOR AN EXPORT OF 2,147 CUBIC YARDS
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/25/2025
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2020 | DAN RYAN EVANGELISTA |
| Corrections Issued | 3/2/2020 | DAN RYAN EVANGELISTA |
| Applicant returned to address corrections | 1/6/2021 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 4/28/2021 | DAN RYAN EVANGELISTA |
| Issued | 4/29/2021 | APPLICANT |
| Permit Finaled | 9/25/2025 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 10/21/2020 | RUBEN VASQUEZ |
| Grading Pre-Inspection | Cleared | 1/6/2021 | ROBERT HUGHES |
| Landscape for retaining wall | Cleared | 4/12/2021 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 4/14/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | JEANIE LAM |
| Permit | Cleared | 4/21/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/21/2021 | WALLIE JONG |
| Excavation more than 5-ft deep | Cleared | 4/28/2021 | CALOSHA APPROVED |
| Haul Route | Cleared | 4/28/2021 | VERONICA LOPEZ |
Contact Information
| Contractor | Padilla'S Company Inc; Lic. No.: 564257-C12 | 667 ARROYO AVE SAN FERNANDO, CA 91340 |
| Engineer | Tosounian,, Oshin Bedros; Lic. No.: C43739 | 7136 HASKELL AVE STE 301 VAN NUYS, CA 91406 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/26/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 6/7/2021 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 6/11/2021 | Partial Approval | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/10/2021 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 9/15/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 9/23/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 9/24/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 10/5/2021 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 10/5/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 11/22/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 11/23/2021 | Approved | ROBERT HUGHES |
| Deputy Grading | 11/24/2021 | Approved | ROBERT HUGHES |
| Sub-Drain | 1/14/2022 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/11/2022 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 6/8/2022 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 8/16/2022 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 12/20/2023 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 1/31/2024 | Partial Approval | MICHAEL TEMPLE |
| Drainage Devices/Catch Basin | 3/15/2024 | Partial Approval | LANNY MERRICK |
| Drainage Devices/Catch Basin | 1/16/2025 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 8/27/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 8/27/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Rough | 8/27/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 9/10/2025 | Approved | RAMAZANALI ALMASI |
| Approved Compaction Report | 9/11/2025 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 9/25/2025 | Approved | RAMAZANALI ALMASI |
| Final | 9/25/2025 | Permit Finaled | RAMAZANALI ALMASI |