1316-1322 N DOUGLAS ST 90026

Certificate Information: 1316-1322 N DOUGLAS ST 90026

Application / Permit
20030-10000-01201
Plan Check / Job No.
G20LA00052
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING FOR 10 LOT SUBDIVISION. CUT = 2,545 CY.; FILL = 115 CY; R&R = 1,425 CY.; EXPORT = 2145 CY 1 OF 3 BF 180048 APPROVED FOR AN EXPORT OF 2,147 CUBIC YARDS
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
Permit Finaled on 9/25/2025

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/2/2020 DAN RYAN EVANGELISTA
Corrections Issued 3/2/2020 DAN RYAN EVANGELISTA
Applicant returned to address corrections 1/6/2021 DAN RYAN EVANGELISTA
Plan Check Approved 4/28/2021 DAN RYAN EVANGELISTA
Issued 4/29/2021 APPLICANT
Permit Finaled 9/25/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

Tract Map conditions Cleared 10/21/2020 RUBEN VASQUEZ
Grading Pre-Inspection Cleared 1/6/2021 ROBERT HUGHES
Landscape for retaining wall Cleared 4/12/2021 DENZEL HENDERSON
Low Impact Development Cleared 4/14/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 4/20/2021 JEANIE LAM
Permit Cleared 4/21/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 4/21/2021 WALLIE JONG
Excavation more than 5-ft deep Cleared 4/28/2021 CALOSHA APPROVED
Haul Route Cleared 4/28/2021 VERONICA LOPEZ

Contact Information

Contractor Padilla'S Company Inc; Lic. No.: 564257-C12 667 ARROYO AVE      SAN FERNANDO, CA 91340
Engineer Tosounian,, Oshin Bedros; Lic. No.: C43739 7136 HASKELL AVE STE 301      VAN NUYS, CA 91406
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/26/2021 Approved ROBERT HUGHES
Bottom/Toe 6/7/2021 Partial Approval ALEXANDER HELFER
Bottom/Toe 6/11/2021 Partial Approval ALEXANDER HELFER
Drainage Devices/Catch Basin 8/10/2021 Partial Approval ROBERT HUGHES
Bottom/Toe 9/15/2021 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 9/23/2021 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 9/24/2021 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/5/2021 Partial Approval ROBERT HUGHES
Fill/Backfill 10/5/2021 Partial Approval ROBERT HUGHES
Deputy Grading 11/22/2021 Approved ROBERT HUGHES
Deputy Grading 11/23/2021 Approved ROBERT HUGHES
Deputy Grading 11/24/2021 Approved ROBERT HUGHES
Sub-Drain 1/14/2022 Partial Approval ROBERT HUGHES
Sub-Drain 4/11/2022 Partial Approval ROBERT HUGHES
Sub-Drain 6/8/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 8/16/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 12/20/2023 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 1/31/2024 Partial Approval MICHAEL TEMPLE
Drainage Devices/Catch Basin 3/15/2024 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 1/16/2025 Partial Approval LANNY MERRICK
Bottom/Toe 8/27/2025 Not Ready for Inspection RAMAZANALI ALMASI
Final 8/27/2025 Not Ready for Inspection RAMAZANALI ALMASI
Rough 8/27/2025 Not Ready for Inspection RAMAZANALI ALMASI
Approved Compaction Report 9/10/2025 Approved RAMAZANALI ALMASI
Approved Compaction Report 9/11/2025 Approved RAMAZANALI ALMASI
Bottom/Toe 9/25/2025 Approved RAMAZANALI ALMASI
Final 9/25/2025 Permit Finaled RAMAZANALI ALMASI
Rough 9/25/2025 Approved RAMAZANALI ALMASI