1106 S KENMORE AVE 90006
Certificate Information: 1106 S KENMORE AVE 90006
- Application / Permit
- 20030-10000-00743
- Plan Check / Job No.
- B19SL01746
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for Site Preparation.
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/1/2025
Permit Application Status History
| Submitted | 12/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | SALVADOR QUINTANILLA |
| Disabled Access Plans Picked Up | 1/31/2020 | APPLICANT |
| Corrections Issued | 2/10/2020 | SALVADOR QUINTANILLA |
| Quality Review Completed | 2/12/2020 | KEN GILL |
| Applicant returned to address corrections | 3/19/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/24/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/25/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/2/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/3/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/24/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/25/2020 | SALVADOR QUINTANILLA |
| Green Plans Picked Up | 12/16/2020 | APPLICANT |
| Applicant returned to address corrections | 5/26/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 5/27/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/22/2021 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/2/2021 | SALVADOR QUINTANILLA |
| Issued | 11/29/2021 | APPLICANT |
| Building Plans Picked Up | 12/14/2021 | APPLICANT |
| Permit Finaled | 3/28/2025 | JONATHAN HOM |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | New Creation Engineering & Builders Inc; Lic. No.: 768842-B | 17809 CLARK AVENUE BELLFLOWER, CA 90706 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/9/2022 | Approved | LANNY MERRICK |
| Deputy Grading | 2/10/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 2/11/2022 | Conditional Approval | LANNY MERRICK |
| Fill/Backfill | 2/11/2022 | Partial Approval | LANNY MERRICK |
| Excavation | 2/15/2022 | Partial Inspection | LANNY MERRICK |
| Initial Grading | 2/15/2022 | Approved | LANNY MERRICK |
| Fill/Backfill | 2/17/2022 | Approved | LANNY MERRICK |
| Initial Grading | 2/17/2022 | Approved | LANNY MERRICK |
| Drainage Devices/Catch Basin | 3/1/2022 | Not Ready for Inspection | LANNY MERRICK |
| Special/Order Compliance | 3/4/2022 | Approved | LANNY MERRICK |
| Bottom/Toe | 3/18/2022 | Conditional Approval | LANNY MERRICK |
| Special/Order Compliance | 4/7/2022 | Partial Inspection | LANNY MERRICK |
| Special/Order Compliance | 4/19/2022 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 8/30/2024 | Approved | JONATHAN HOM |
| Deputy Grading | 9/30/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/12/2025 | Partial Approval | JONATHAN HOM |
| Rough | 2/12/2025 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 3/7/2025 | Partial Inspection | JONATHAN HOM |
| Final | 3/7/2025 | Partial Inspection | JONATHAN HOM |
| Rough | 3/7/2025 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 3/28/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 3/28/2025 | Approved | JONATHAN HOM |
| Final | 3/28/2025 | Permit Finaled | JONATHAN HOM |
| Rough | 3/28/2025 | Approved | JONATHAN HOM |