2840 E LUGO ST 90023

Certificate Information: 2840 E LUGO ST 90023

Application / Permit
20030-10000-00567
Plan Check / Job No.
B19LA27271
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading for proposed building, Removal and Recompaction and Retaning Wall
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
Permit Finaled on 2/9/2023

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 HERNAN ARREOLA
Corrections Issued 1/29/2020 HERNAN ARREOLA
Quality Review Completed 2/5/2020 BILL STUTSMAN
Building Plans Picked Up 2/6/2020 APPLICANT
Plan Check Approved 6/17/2020 HERNAN ARREOLA
Issued 5/12/2021 APPLICANT
Permit Finaled 2/8/2023 LANNY MERRICK

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Anvil Construction Company Inc; Lic. No.: 998987-B 8895 RESEARCH DRIVE      IRVINE, CA 92618
Engineer Anderson,, Brett Leslie; Lic. No.: C45389 77009 CALIFORNIA DR      PALM DESERT, CA 92211
Engineer Dizon,, Marites Avante; Lic. No.: C61180 3518 ATWATER AVE      LOS ANGELES, CA 90039

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 6/11/2021 Approved ALEXANDER HELFER
Excavation 6/11/2021 Approved ALEXANDER HELFER
Initial Grading 6/11/2021 Approved ALEXANDER HELFER
Bottom/Toe 6/14/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/14/2021 Approved ROBERT HUGHES
Deputy Grading 6/15/2021 Approved ROBERT HUGHES
Bottom/Toe 6/16/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/16/2021 Approved ROBERT HUGHES
Bottom/Toe 6/17/2021 Not Ready for Inspection ROBERT HUGHES
Deputy Grading 6/17/2021 Approved ROBERT HUGHES
Bottom/Toe 6/18/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/18/2021 Approved ROBERT HUGHES
Bottom/Toe 6/21/2021 Not Ready for Inspection ROBERT HUGHES
Deputy Grading 6/21/2021 Approved ROBERT HUGHES
Bottom/Toe 6/22/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/22/2021 Approved ROBERT HUGHES
Bottom/Toe 6/23/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/23/2021 Approved ROBERT HUGHES
Bottom/Toe 6/24/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/24/2021 Approved ROBERT HUGHES
Deputy Grading 6/25/2021 Approved ROBERT HUGHES
Bottom/Toe 6/28/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/28/2021 Approved ROBERT HUGHES
Bottom/Toe 6/29/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/29/2021 Approved ROBERT HUGHES
Bottom/Toe 6/30/2021 Partial Approval ROBERT HUGHES
Deputy Grading 6/30/2021 Approved ROBERT HUGHES
Deputy Grading 7/1/2021 Approved ROBERT HUGHES
Initial Grading 7/1/2021 Partial Approval ROBERT HUGHES
Bottom/Toe 7/2/2021 Partial Approval ROBERT HUGHES
Deputy Grading 7/2/2021 Approved ROBERT HUGHES
Bottom/Toe 7/13/2021 Partial Approval ROBERT HUGHES
Bottom/Toe 7/15/2021 Partial Approval ROBERT HUGHES
Initial Grading 7/16/2021 Approved ROBERT HUGHES
Bottom/Toe 7/19/2021 Partial Approval ROBERT HUGHES
Bottom/Toe 7/28/2021 Partial Approval ROBERT HUGHES
Approved Compaction Report 8/20/2021 Approved ROBERT HUGHES
Bottom/Toe 9/17/2021 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 2/25/2022 Partial Inspection LANNY MERRICK
Drainage Devices/Catch Basin 6/16/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 6/17/2022 Not Ready for Inspection ROBERT HUGHES
Fill/Backfill 6/17/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 6/27/2022 Partial Approval MATTHEW JENKINS
Bottom/Toe 7/6/2022 Partial Approval KIRK LINKLATER
Drainage Devices/Catch Basin 7/6/2022 Partial Approval KIRK LINKLATER
Drainage Devices/Catch Basin 7/7/2022 Partial Inspection MATTHEW JENKINS
Sub-Drain 7/7/2022 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 7/11/2022 Partial Inspection MATTHEW JENKINS
Sub-Drain 7/11/2022 Partial Approval MATTHEW JENKINS
Bottom/Toe 9/9/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 10/13/2022 Not Ready for Inspection ROBERT HUGHES
Special/Order Compliance 10/13/2022 Not Ready for Inspection ROBERT HUGHES
Bottom/Toe 12/19/2022 Approved ROBERT HUGHES
Drainage Devices/Catch Basin 12/19/2022 Partial Approval ROBERT HUGHES
Final 12/19/2022 Not Ready for Inspection ROBERT HUGHES
Irrigation/Landscape 12/19/2022 Approved ROBERT HUGHES
Rough 12/19/2022 Approved ROBERT HUGHES
Final 1/12/2023 Not Ready for Inspection LANNY MERRICK
Final 1/17/2023 Corrections Issued LANNY MERRICK
Final 2/8/2023 Permit Finaled LANNY MERRICK