11350 W PALMS BLVD 90066
Certificate Information: 11350 W PALMS BLVD 90066
- Application / Permit
- 20030-10000-00416
- Plan Check / Job No.
- B20LA01219
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING (INC.R&R) <<Ref.18010-20000-06288>>>
- Permit Issued
- Issued on 5/26/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 11/17/2021
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | DEAN LEE |
| Corrections Issued | 1/23/2020 | DEAN LEE |
| Plan Check Approved | 2/21/2020 | DEAN LEE |
| Issued | 5/26/2020 | LADBS |
| Permit Finaled | 11/16/2021 | AL GAMBLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/24/2019 | DEAN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | JEANETTE VONG |
| Low Impact Development | Cleared | 1/28/2020 | ANDRES COVARRUBIAS |
Contact Information
| Architect | Fisher,, John S; Lic. No.: C4487 | 5567 RESEDA BLVD # 209 TARZANA, CA 91356 |
| Contractor | Driver S P G Llc; Lic. No.: 960119-B | 468 NORTH ROSEMEAD BLVD PASADENA, CA 91107 |
| Engineer | Sagherian,, Jonathan Hovnathan; Lic. No.: C37138 | 444 PIEDMONT AVE 203 GLENDALE, CA 91206 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/4/2020 | Approved | JONATHAN HOM |
| Deputy Grading | 6/10/2020 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/11/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation | 6/11/2020 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/12/2020 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/12/2020 | Approved | MATTHEW JENKINS |
| Excavation | 6/12/2020 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 6/16/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation | 6/17/2020 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/19/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation | 6/19/2020 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/22/2020 | Approved | KIRK LINKLATER |
| Excavation | 6/23/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation | 6/25/2020 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/29/2020 | Approved | KIRK LINKLATER |
| Approved Compaction Report | 7/24/2020 | Approved | AL GAMBLE |
| Approved Compaction Report | 11/13/2020 | Partial Inspection | MATTHEW JENKINS |
| Fill/Backfill | 11/13/2020 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 12/4/2020 | Approved | KIRK LINKLATER |
| Private Sewage Disposal System | 3/2/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 3/2/2021 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 3/12/2021 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 3/12/2021 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 6/16/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 6/16/2021 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 6/22/2021 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 6/22/2021 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 7/20/2021 | Partial Approval | AL GAMBLE |
| Fill/Backfill | 7/20/2021 | Partial Approval | AL GAMBLE |
| Bottom/Toe | 7/22/2021 | Not Ready for Inspection | AL GAMBLE |
| Sub-Drain | 7/22/2021 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 7/30/2021 | Partial Approval | AL GAMBLE |
| Drainage Devices/Catch Basin | 7/30/2021 | Partial Approval | AL GAMBLE |
| Sub-Drain | 8/19/2021 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 11/3/2021 | Approved | AL GAMBLE |
| Bottom/Toe | 11/16/2021 | Approved | AL GAMBLE |
| Final | 11/16/2021 | Permit Finaled | AL GAMBLE |
| Rough | 11/16/2021 | Approved | AL GAMBLE |