1660 W ANAHEIM ST 90731

Certificate Information: 1660 W ANAHEIM ST 90731

Application / Permit
20026-30000-00364
Plan Check / Job No.
B20WL04570
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
Alteration/Repair of existing structure to support new selective catalytic reduction (SCR) NOx reduction equipment for existing Boiler-6. Modify Foundation to support aditional weight of SCR the new mat foundation has been design and epoxy attached to the existing boiler 6 foundation
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
Permit Finaled on 11/17/2022

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 SERGIO SILVA
Corrections Issued 11/23/2020 SERGIO SILVA
Quality Review Completed 12/4/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/8/2020 APPLICANT
Applicant returned to address corrections 2/18/2021 SERGIO SILVA
Applicant returned to address corrections 4/13/2021 SERGIO SILVA
Plan Check Approved 6/3/2021 SERGIO SILVA
Issued 6/22/2021 APPLICANT
Permit Finaled 11/17/2022 JOEY BUCHANAN

Permit Application Clearance Information

"Q" conditions Cleared 2/25/2021 LOUIS ORTEGA
ZI Cleared 2/25/2021 LOUIS ORTEGA
Abandoned oil well Cleared 5/28/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 6/2/2021 SERGIO SILVA

Contact Information

Contractor Arb Inc; Lic. No.: 194079-C51 26000 COMMERCENTRE DRIVE      LAKE FOREST, CA 92630
Engineer Patil,, Uday Keshav; Lic. No.: GE670 4011 P V DRIVE SOUTH      RANCHO PALOS VERDES, CA 90275
Engineer Yamanoha,, Steven Hideo; Lic. No.: C27400 3602 MARIN DR      IRVINE, CA 92714

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2021 Approved NICK LAROCCA
Deputy Drilled-In Anchors 8/13/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 8/13/2021 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 8/16/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 8/16/2021 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 8/17/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 8/17/2021 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 8/18/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 8/18/2021 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 8/19/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 8/19/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 8/26/2021 Not Ready for Inspection NICK LAROCCA
Footing/Foundation/Slab 8/30/2021 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 9/9/2021 Approved NICK LAROCCA
Footing/Foundation/Slab 9/21/2021 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 1/6/2022 Approved NICK LAROCCA
Deputy Steel/Welding 1/6/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/7/2022 Approved NICK LAROCCA
Deputy Steel/Welding 1/7/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/10/2022 Approved NICK LAROCCA
Deputy Steel/Welding 1/10/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/11/2022 Approved NICK LAROCCA
Deputy Steel/Welding 1/11/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/12/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/12/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 3/22/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 3/23/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 4/14/2022 Approved JOEY BUCHANAN
Deputy Other (see comments) 6/14/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 6/14/2022 Approved JOEY BUCHANAN
Deputy Other (see comments) 6/15/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 6/15/2022 Approved JOEY BUCHANAN
Deputy Other (see comments) 6/16/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 6/16/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 8/8/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 8/9/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 8/10/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 8/11/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 8/12/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 9/21/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/22/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/23/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/26/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/27/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/28/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/29/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/30/2022 Conditional Approval JOEY BUCHANAN
Final 11/17/2022 Permit Finaled JOEY BUCHANAN