1409 N SANBORN AVE 90027
Certificate Information: 1409 N SANBORN AVE 90027
- Application / Permit
- 20020-30000-02625
- Plan Check / Job No.
- B20WL05425
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- 2 new retaining walls max 10 ft high
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/23/2022
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | REZA HAGHIGHAT |
| Corrections Issued | 12/28/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/7/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/15/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/16/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 2/14/2022 | REZA HAGHIGHAT |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Permit Finaled | 11/23/2022 | MATTHEW JENKINS |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 12/7/2021 | RUBEN VASQUEZ |
| Excavation more than 5-ft deep | Cleared | 12/14/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 12/14/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 1453 14TH ST STE A SANTA MONICA, CA 90404 |
| Geologist | , ; Lic. No.: GEO2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Haenschke,, Eirik Francis; Lic. No.: EG1597 | 9616 GIERSON AVE CHATSWORTH, CA 91311 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Partial Approval | ROBERT HUGHES |
| Pre-Inspection | 5/16/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/19/2022 | Conditional Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 5/25/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 6/7/2022 | Conditional Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 6/9/2022 | Partial Approval | ROBERT HUGHES |
| Pre-Inspection | 6/9/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 6/13/2022 | Partial Approval | ROBERT HUGHES |
| Pre-Inspection | 6/13/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 6/15/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Footing/Foundation/Slab | 6/21/2022 | Partial Approval | ROBERT HUGHES |
| Special/Order Compliance | 8/2/2022 | Partial Approval | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Partial Approval | ROBERT HUGHES |
| Final | 10/19/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 11/23/2022 | Permit Finaled | MATTHEW JENKINS |