1000 N CASIANO ROAD 90049
Certificate Information: 1000 N CASIANO ROAD 90049
- Application / Permit
- 20020-30000-02162
- Plan Check / Job No.
- B20WL04524
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- new retaining wall per city of la fig.#2
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/3/2021
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 10/26/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 10/26/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/21/2020 | APPLICANT |
| Applicant returned to address corrections | 3/16/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 3/22/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/23/2021 | APPLICANT |
| Permit Finaled | 12/3/2021 | CHARLES POWELL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | DINAH GARIN |
| Miscellaneous | Cleared | 2/9/2021 | JENSON LEE |
| Excavation more than 5-ft deep | Cleared | 3/22/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Haddad,, Raymond Mounir; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 5841 ETIWANDA AVE TARZANA, CA 91356 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | BRIAN OLSON |
| Deputy Reinf. Concrete | 5/12/2021 | Approved | BRIAN OLSON |
| Masonry Wall/Backfill | 5/18/2021 | Partial Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 5/21/2021 | Partial Approval | BRIAN OLSON |
| Deputy Reinf. Concrete | 5/24/2021 | Approved | BRIAN OLSON |
| Masonry Wall/Backfill | 5/26/2021 | Partial Approval | BRIAN OLSON |
| Reinforced Masonry Frame | 5/27/2021 | Partial Approval | BRIAN OLSON |
| Deputy Reinf. Masonry | 5/28/2021 | Conditional Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 6/3/2021 | Partial Approval | BRIAN OLSON |
| Footing/Foundation/Slab | 6/9/2021 | Partial Approval | BRIAN OLSON |
| Deputy Reinf. Concrete | 6/10/2021 | Conditional Approval | BRIAN OLSON |
| Deputy Reinf. Masonry | 6/11/2021 | Conditional Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 6/11/2021 | Partial Approval | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Partial Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 6/23/2021 | Partial Approval | BRIAN OLSON |
| Deputy Reinf. Concrete | 6/24/2021 | Conditional Approval | BRIAN OLSON |
| Reinforced Masonry Frame | 6/25/2021 | Partial Approval | BRIAN OLSON |
| Final | 7/14/2021 | Partial Inspection | JONATHAN HOM |
| Final | 12/1/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 12/3/2021 | Permit Finaled | CHARLES POWELL |