12324 W 25TH HELENA DR 90049
Certificate Information: 12324 W 25TH HELENA DR 90049
- Application / Permit
- 20020-30000-01540
- Plan Check / Job No.
- B20WL03132
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Permanent)
- Work Description
- Shoring for new SFD with basement.
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/29/2024
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | MANUEL GARCIA |
| Corrections Issued | 8/31/2020 | MANUEL GARCIA |
| Quality Review Completed | 9/14/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/14/2020 | MANUEL GARCIA |
| Building Plans Picked Up | 10/19/2020 | APPLICANT |
| Applicant returned to address corrections | 11/25/2020 | MANUEL GARCIA |
| Plan Check Approved | 1/12/2021 | MANUEL GARCIA |
| Issued | 2/4/2021 | APPLICANT |
| Permit Finaled | 2/29/2024 | ARAM AVEDISIAN |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 11/10/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/24/2020 | MANUEL GARCIA |
| Grading Pre-Inspection | Cleared | 11/24/2020 | MANUEL GARCIA |
| Excavation more than 5-ft deep | Cleared | 1/12/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Barber,, Charles Timothy; Lic. No.: C29232 | 829 N HARPER AVENUE LOS ANGELES, CA 90046 |
| Contractor | Premier General Contractors Inc; Lic. No.: 638046-B | 1131 N GRANADA AVE ALHAMBRA, CA 91801 |
| Engineer | Ruan,, Federico R; Lic. No.: S6689 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 3/5/2021 | Approved | ROBERT SHELLY |
| Piling/Pier/Caisson | 3/24/2021 | Partial Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 6/29/2021 | Partial Approval | JUAN VALENZUELA |
| Final | 11/28/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 2/29/2024 | Permit Finaled | ARAM AVEDISIAN |