10104 W ANGELO VIEW DR 90210
Certificate Information: 10104 W ANGELO VIEW DR 90210
- Application / Permit
- 20020-30000-01445
- Plan Check / Job No.
- B20WL02940
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- new on grade structural concrete deck
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/9/2023
Permit Application Status History
| Submitted | 7/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 8/3/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 8/4/2020 | CHIHARU SUZUKI |
| Plan Check Approved | 9/15/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| Refund Closed | 11/2/2020 | MARY SUM |
| Issued | 11/2/2020 | MARY SUM |
| Refund in Progress-Status Void | 11/5/2020 | CHRISTINA TABIRARA |
| Re-Activate Permit | 11/17/2020 | MARY SUM |
| Refund Completed-Status Void | 3/11/2021 | MARY SUM |
| Re-Activate Permit | 6/1/2021 | MARY SUM |
| Permit Finaled | 6/10/2021 | ANTHONY MCDOWALL |
| CofO in Progress | 6/10/2021 | ANTHONY MCDOWALL |
| No Progress | 2/9/2023 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2020 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | NIKTA MOUSAVI |
| Hold | Cleared | 6/1/2021 | MARY SUM |
Contact Information
| Engineer | Nasser,, Andrew Richard; Lic. No.: S1453 | 479 S MARENGO AVE PASADENA, CA 91101 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/11/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 3/17/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/12/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | JUAN VALENZUELA |
| Final | 6/3/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Final | 6/10/2021 | Permit Finaled | ANTHONY MCDOWALL |