Pre-Inspection
|
2/11/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Piling/Pier/Caisson
|
2/25/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
2/26/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Deputy Grading
|
3/24/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2021
|
Not Ready for Inspection
|
TIMOTHY BUXTON
|
|
Deputy Grading
|
3/25/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Grading
|
3/26/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/30/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
5/19/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/21/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
5/24/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/25/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/26/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/27/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
6/2/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
6/23/2021
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/23/2021
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
9/22/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
10/14/2021
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Shotcrete
|
10/19/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/22/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/23/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
12/2/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
12/6/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/10/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/11/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/13/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/14/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2022
|
Corrections Issued
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/20/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/21/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/24/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/31/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/7/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
2/8/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/11/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/16/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/17/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
2/22/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/22/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
2/23/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/25/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/2/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/4/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/23/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
3/24/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
3/25/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
3/29/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/30/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/1/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/4/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/6/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/7/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
4/8/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
4/8/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
4/25/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
4/27/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/28/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
4/28/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/29/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
4/29/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/2/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/2/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/3/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/3/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/4/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/4/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/5/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/5/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/6/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/6/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/9/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/9/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
5/13/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/13/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
5/17/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/17/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
5/18/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/18/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
5/19/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/19/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
5/20/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/20/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
5/23/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/23/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/25/2022
|
Conditional Approval
|
TERRY HERR
|
|
Deputy Shotcrete
|
5/26/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/31/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
6/1/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/9/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/10/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/13/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/14/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/15/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/16/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/17/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
6/22/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Pre-Inspection
|
6/22/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
6/22/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
6/23/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/27/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/28/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
6/29/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/29/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
6/29/2022
|
Approved
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
6/30/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/30/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
7/1/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/5/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/6/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/7/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/8/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
7/8/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
7/8/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
7/11/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/12/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
7/13/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Pre-Stress Concrete
|
7/14/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
7/14/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
7/15/2022
|
Conditional Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
7/15/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Pre-Stress Concrete
|
7/18/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Reinf. Concrete
|
7/18/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
7/19/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
7/20/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
7/21/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Pre-Stress Concrete
|
7/22/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Reinf. Concrete
|
8/16/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
8/16/2022
|
Approved
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/16/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2022
|
Off-Hour Fees Due
|
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Drilled-In Anchors
|
8/19/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
8/19/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
8/31/2022
|
Approved
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/31/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
9/21/2022
|
Approved
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
10/3/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
10/3/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
10/25/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
10/28/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
11/2/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
1/17/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Grading
|
5/7/2024
|
Partial Approval
|
ADAM BURGESS
|
|
Piling/Pier/Caisson
|
5/13/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
12/24/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Final
|
11/12/2025
|
Permit Finaled
|
DAVID BURKHEAD
|