2188 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2188 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 20020-30000-01292
- Plan Check / Job No.
- B20WL02512
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- New subterranean utility vault under driveway
- Permit Issued
- Issued on 8/7/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/21/2021
Permit Application Status History
| Submitted | 6/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/21/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 7/28/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/7/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 8/7/2020 | APPLICANT |
| Permit Finaled | 7/21/2021 | JUAN VALENZUELA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2020 | MAHELET GEBEYHU |
| Watercourse | Cleared | 7/23/2020 | MAHELET GEBEYHU |
Contact Information
| Contractor | Hill Pete Construction Company Inc; Lic. No.: 470065-B | 4626 ALBUQUERQUE ST 2ND FLOOR SAN DIEGO, CA 92109 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 12/1/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/2/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/3/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/9/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 12/10/2020 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 12/31/2020 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 1/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/5/2021 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 1/7/2021 | Conditional Approval | MATT KELLERMAN |
| Final | 6/23/2021 | Conditional Approval | JUAN VALENZUELA |