845 S ST ANDREWS PL 90005
Certificate Information: 845 S ST ANDREWS PL 90005
- Application / Permit
- 20020-30000-00952
- Plan Check / Job No.
- B20WL01881
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Shoring for new apartment building
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/23/2025
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | MARJAN SHENASI |
| Corrections Issued | 5/26/2020 | MARJAN SHENASI |
| Quality Review Completed | 6/3/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/15/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 1/14/2021 | MARJAN SHENASI |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Plan Check Approved | 5/10/2021 | MARJAN SHENASI |
| Issued | 12/20/2021 | APPLICANT |
| Permit Finaled | 4/23/2025 | EDWIN GREGORYONA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/5/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2020 | JEANIE LAM |
| Work Adjacent to Public Way | Cleared | 2/16/2021 | CHIU TAM |
| Excavation more than 5-ft deep | Cleared | 4/21/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Sma Builders Inc; Lic. No.: 457725-B | 16134 LEADWELL ST VAN NUYS, CA 91406 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Benichou,, Ety; Lic. No.: S5263 | 888 S FIGUEROA ST 18TH FLOOR LOS ANGELES, CA 90017 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 1/11/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Grading | 1/12/2022 | Conditional Approval | JONATHAN QUACH |
| Deputy Grading | 1/13/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Grading | 1/13/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Grading | 1/14/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Grading | 1/18/2022 | Conditional Approval | DARRYL ARNOLD |