3800 S METTLER ST 90011
Certificate Information: 3800 S METTLER ST 90011
- Application / Permit
- 20020-30000-00790
- Plan Check / Job No.
- B20WL01615
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALLATION OF 13,000 GALLONS LIQUID NITROGEN TANK W/ NEW CONCRETED FOUNDATION
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- Issued on 7/7/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | TARIK SAOUD |
| Corrections Issued | 5/13/2020 | TARIK SAOUD |
| Quality Review Completed | 5/21/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/25/2020 | TARIK SAOUD |
| Issued | 7/7/2020 | APPLICANT |
| Building Plans Picked Up | 7/8/2020 | APPLICANT |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 5/26/2020 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 6/5/2020 | SAM NAVID |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | JEANIE LAM |
| ZA Case | Cleared | 6/15/2020 | PABLO ESTRADA |
| Flood clearance | Cleared | 6/17/2020 | RAYMOND LAM |
| Redevelopment Project Area | Cleared | 6/17/2020 | DAVID URITA |
Contact Information
| Contractor | Areio Inc; Lic. No.: 997015-B | 1440 S COAST HIGHWAY LAGUNA BEACH, CA 92651 |
| Engineer | Gordin,, Vyacheslav Steve; Lic. No.: S4311 | 2081 BUSINESS CENTER DRIVE STE 105 IRVINE, CA 92612 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2020 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 7/22/2020 | Corrections Issued | LANNY MERRICK |
| Footing/Foundation/Slab | 7/23/2020 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 8/4/2020 | Partial Approval | LANNY MERRICK |
| Deputy Steel/Welding | 8/13/2020 | Partial Approval | LANNY MERRICK |