7835 S GLORIA AVE 91406
Certificate Information: 7835 S GLORIA AVE 91406
- Application / Permit
- 20020-30000-00773
- Plan Check / Job No.
- B20WL01576
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) Entrance structure
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofO Issued on 12/31/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | MARJAN SHENASI |
| Corrections Issued | 5/4/2020 | MARJAN SHENASI |
| Quality Review Completed | 5/11/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 7/1/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/14/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/18/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/26/2020 | MARJAN SHENASI |
| Plan Check Approved | 10/6/2020 | MARJAN SHENASI |
| Issued | 10/20/2020 | APPLICANT |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| CofO in Progress | 12/31/2020 | JEFFREY FULTON |
| Permit Finaled | 12/31/2020 | JEFFREY DURAN |
| CofO Issued | 12/31/2020 | JEFFREY DURAN |
| Permit Finaled | 12/31/2020 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/13/2020 | DENZEL HENDERSON |
| "T" removal | Cleared | 5/13/2020 | DENZEL HENDERSON |
| City owned building/parcel | Cleared | 7/7/2020 | HAROOT AVANESIAN |
| Miscellaneous | Cleared | 9/17/2020 | ANDREW KO |
Contact Information
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 10/22/2020 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 10/22/2020 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 10/28/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 10/28/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 12/15/2020 | OK to Issue CofO | JEFFREY FULTON |