818 W 7TH ST 90017
Certificate Information: 818 W 7TH ST 90017
- Application / Permit
- 20020-30000-00389
- Plan Check / Job No.
- B20WL00821
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Fence Wall
- Work Description
- New 12 ft high fence wall at property line Facing Flower street and adjacent to parking ramp
- Permit Issued
- Issued on 10/22/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/27/2021
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | REZA HAGHIGHAT |
| Corrections Issued | 3/11/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 3/19/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/1/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 8/26/2020 | REZA HAGHIGHAT |
| Issued | 10/22/2020 | APPLICANT |
| Building Plans Picked Up | 10/23/2020 | APPLICANT |
| Permit Finaled | 7/27/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| "D" conditions | Cleared | 6/22/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 6/22/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 6/22/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 6/22/2020 | DENZEL HENDERSON |
| Metro Rail approval | Cleared | 6/30/2020 | REZA HAGHIGHAT |
| ZI | Cleared | 8/10/2020 | YI LU |
| City Hist. Cultural Monument | Cleared | 8/11/2020 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 8/11/2020 | LAMBERT GIESSINGER |
Contact Information
| Contractor | Pacific Tusk Builders Corp; Lic. No.: 946368-B | 1100 QUAIL ST NEWPORT BEACH, CA 92660 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
| Landscape Architect | Tessier,, Mark; Lic. No.: LA5043 | 1424 4TH ST STE 300 SANTA MONICA, CA 90401 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/14/2021 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 1/20/2021 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 2/26/2021 | Approved | DANIEL COLLINS |
| Deputy Steel/Welding | 6/14/2021 | Conditional Approval | KATY RAMIREZ |
| Masonry Wall/Backfill | 7/22/2021 | Approved | DANIEL COLLINS |
| Structural Steel Frame | 7/22/2021 | Approved | DANIEL COLLINS |
| Final | 7/27/2021 | Permit Finaled | DANIEL COLLINS |