3361 S ROSEWOOD AVE 90066

Certificate Information: 3361 S ROSEWOOD AVE 90066

Application / Permit
20020-30000-00184
Plan Check / Job No.
B20WL00345
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) RETAINING WALL.
Permit Issued
Issued on 4/16/2020
Issuing Office
Current Status
Permit Finaled on 7/26/2022

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 ALFREDO JARA
Corrections Issued 2/24/2020 ALFREDO JARA
Quality Review Completed 3/6/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/8/2020 ALFREDO JARA
Building Plans Picked Up 4/14/2020 APPLICANT
Issued 4/16/2020 APPLICANT
Permit Finaled 7/25/2022 TIMOTHY POWELL

Permit Application Clearance Information

CPC Cleared 4/3/2020 LOUIS ORTEGA
Grading Pre-Inspection Cleared 4/8/2020 ALFREDO JARA

Contact Information

Contractor Greeniron Constructs Inc; Lic. No.: 942902-B 3200 AIRPORT AVENUE STE 20      SANTA MONICA, CA 90405
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/14/2020 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/27/2020 Partial Approval KIRK LINKLATER
Masonry Wall/Backfill 6/4/2020 Partial Approval KIRK LINKLATER
Deputy Grading 6/15/2020 Approved KIRK LINKLATER
Excavation/Setback/Form/Re-Bar 6/15/2020 Partial Approval KIRK LINKLATER
Masonry Wall/Backfill 6/18/2020 Partial Approval KIRK LINKLATER
Excavation/Setback/Form/Re-Bar 6/26/2020 Approved JONATHAN HOM
Excavation/Setback/Form/Re-Bar 7/2/2020 Partial Approval MATTHEW JENKINS
Final 5/9/2022 Partial Inspection JONATHAN HOM
Final 7/25/2022 Permit Finaled TIMOTHY POWELL